- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-23

---

A **bid bond** is a surety bond a contractor submits with its bid to guarantee that, if it is selected, it will sign the contract at its bid price and provide the required [performance](https://essential.construction/academy/glossary/performance-bond/) and [payment bonds](https://essential.construction/academy/glossary/payment-bond/). If the winning bidder backs out, the surety compensates the owner, up to the bond amount.

Bid bonds are a form of bid security, common on public work and large private tenders. This page is a general explanation; requirements vary by owner, state and country.

## How a bid bond works

1. The bid documents state the bid security required, for example "a bid bond of 10% of the bid price."
2. The contractor asks its surety broker for a bid bond for that job. Contractors with an established surety relationship can usually get one quickly, often at little or no separate charge.
3. The signed bond is submitted with the bid, naming the contractor (principal), the owner (obligee) and the surety.
4. If the contractor is not selected, the bond lapses or is returned.
5. If the contractor is selected, it signs the contract and delivers the performance and payment bonds. The bid bond's job is done.
6. If the selected contractor refuses to sign or can't provide the final bonds, the owner can claim on the bid bond. Depending on the bond form, the surety typically pays the owner's loss, often the difference between that bid and the next acceptable bid, up to the bond's penal sum.

## How much is a bid bond?

The bond amount is set by the owner as a percentage of the bid. US federal construction requires a bid guarantee of at least 20% of the bid price, capped at $3 million (FAR 28.101-2). State, municipal and private owners commonly ask for 5% to 10%. What the contractor pays for it depends on its surety relationship; many sureties charge little or nothing for bid bonds because they expect to write the final bonds if the bid succeeds.

### What does a 5% bid bond mean?

It means the bond's penal sum is 5% of the bid price. On a $2,000,000 bid that is $100,000, which is the most the surety would pay the owner if the bidder defaulted.

## Bid bond vs performance bond

|  | Bid bond | Performance bond |
| --- | --- | --- |
| Guarantees | The bidder will sign the contract and furnish final bonds | The contractor will complete the work per the contract |
| When | Submitted with the bid | Delivered at contract signing |
| Typical amount | A percentage of the bid (5% to 20%) | Usually 100% of the contract price |
| Ends | When the contract and final bonds are signed, or the bid is rejected | After completion and any bonded warranty period |

For all three construction bonds side by side, see the comparison on our [performance bond](https://essential.construction/academy/glossary/performance-bond/) page.

## Alternatives to a bid bond

Bid documents may also accept a certified or cashier's check, a bank draft or an irrevocable letter of credit as bid security. These tie up the contractor's cash or credit line, which is why most contractors prefer a bond. In the UK and some other countries, a "tender bond" or bank guarantee does the same job.

## Tips for bidders

- Read the bid instructions for the exact bond form, amount, wording and whether a power of attorney or seal is required. A defective bid bond can make the bid non-responsive.
- Check the bid validity period. Your bid, and the bond, typically stay open for a set number of days.
- Tell your surety about every bid early, especially large ones, so you stay within your bonding capacity.
- Check your numbers before bid day: a math error is not always a reason to withdraw without forfeiting the bond.

## Bid bond and bidding templates

Bonded bids are won or lost on paperwork: a standard set of bid forms and checks helps you submit a complete, compliant package every time.

- [Bid Bond Template](https://essential.construction/files/pre-construction/estimating/bid-bond-template/)
- [Bid Compliance Certificate](https://essential.construction/files/pre-construction/estimating/bid-compliance-certificate/)
- [Construction Bid Template](https://essential.construction/files/pre-construction/estimating/construction-bid-template/)

New to tendering? Read [Construction Tendering: Everything You Need to Know](https://essential.construction/academy/tutorials/construction-tendering-the-basics/).

## Related terms

- [Performance Bond](https://essential.construction/academy/glossary/performance-bond/)
- [Payment Bond](https://essential.construction/academy/glossary/payment-bond/)
- [Notice to Proceed](https://essential.construction/academy/glossary/notice-to-proceed/)
- [Scope of Work](https://essential.construction/academy/glossary/scope-of-work/)

## Frequently asked questions

### What is the cost of a bid bond?

Many sureties issue bid bonds to established clients for little or no fee, because they expect to write the performance and payment bonds if the bid wins. Contractors without a surety relationship may pay a fee or need to be underwritten first. The bond amount itself is set by the owner.

### What happens if you win a bid and back out?

If you refuse to sign the contract or can't provide the required bonds, the owner can claim on your bid bond. The surety typically pays the owner's loss up to the bond amount, and then recovers that money from you under your indemnity agreement. It can also hurt your bonding capacity.

### Is a bid bond required for all projects?

No. Bid bonds are usually required on public projects and on private projects where the owner asks for them in the bid documents. Many small private jobs have no bid security at all. Always check the instructions to bidders.

### What are the four types of bonds in construction?