# Change Directive [CD]

> What a construction change directive (CCD) is, when owners issue one, how pricing is settled afterward, and the key differences from a change order.

- URL: https://essential.construction/academy/glossary/change-directive/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-03

---

A change directive is a written instruction, issued by the owner or by the consultant on the owner's behalf, that directs the contractor to carry out a change in the work before price or time has been agreed. In the US it is usually called a construction change directive (CCD). It puts the contractor in a position where they must carry out the work, with pricing provided during or after the work.

## When a change directive is used

- The change is urgent and waiting for agreed pricing would delay the job.
- The owner and contractor cannot agree on the cost or time of a proposed change.
- A safety or code issue has to be fixed right away.

## How it works

1. The directive describes the change and states how it will be valued (for example lump sum, unit prices or cost plus a fee).
2. The contractor proceeds with the work.
3. The contractor tracks costs, normally on daily time-and-material sheets signed by the consultant or owner's representative.
4. Pricing and any time impact are submitted and reviewed.
5. Once agreed, the directive is converted into a [change order](https://essential.construction/academy/glossary/change-order/).

The AIA form in the US is G714, Construction Change Directive. Canadian CCDC 2 contracts call it a change directive.

## Change directive vs change order

|  | Change directive | Change order |
| --- | --- | --- |
| Price and time agreed? | No, settled later | Yes, before signing |
| Contractor must proceed? | Yes, on receipt | Once signed |
| Signed by | Owner and consultant | Owner and contractor (and architect on AIA) |
| End result | Becomes a change order once agreed | Final contract adjustment |

## Tips for contractors

- Check the valuation method stated in the directive before starting.
- Keep detailed daily records of labour, equipment and materials, and get them signed.
- Flag schedule impact in writing straight away.
- Log the directive in your change order log so it is not missed at billing.

## Related terms

- [Change Order](https://essential.construction/academy/glossary/change-order/)
- [Site Instruction](https://essential.construction/academy/glossary/site-instruction/)
- [CCN](https://essential.construction/academy/glossary/ccn/)

## Related templates and guides

- [Change Order Log](https://essential.construction/files/construction/administration/change-order-log/)
- [Confirmation of Verbal Instruction](https://essential.construction/files/construction/administration/confirmation-of-verbal-instruction/)
- [Common Types of Construction Contracts and Their Use](https://essential.construction/academy/tutorials/common-types-of-construction-contracts-and-their-use/)

## Frequently asked questions

### Does a contractor have to follow a change directive?

Yes. Under standard contracts such as AIA A201 and CCDC 2, the contractor must proceed with the work described in a change directive even though price and time are not yet agreed. Disagreements over the final valuation are handled afterward through the contract's change and dispute provisions.

### Is a change directive the same as a change order?

No. A change order records an agreed change to scope, price and time. A change directive orders the work before that agreement. Once the parties agree on the adjustment, the change directive is converted into a change order.

### How is the cost of a change directive determined?

The directive should state the method, typically a lump sum, agreed unit prices, or actual cost plus an agreed fee. Where cost-plus is used, the contractor's daily records of labour, materials and equipment become the basis of the final change order.