# Cost-Plus Contract

> A cost-plus contract pays the contractor's actual costs plus a fixed or percentage fee. Types, GMP caps, pros and cons, FAR rules and when to use one.

- URL: https://essential.construction/academy/glossary/cost-plus-contract/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-25

---

A **cost-plus contract** is a construction contract in which the owner pays the contractor's actual cost of the work, such as labor, materials, equipment and subcontracts, plus a fee for overhead and profit. The fee is either a fixed amount or a percentage of cost. The owner takes on most of the cost risk, so it gets open books in return.

It is also called a cost-reimbursement contract or cost of the work plus a fee. The opposite is a lump sum (stipulated sum) contract with one fixed price.

## How a cost-plus contract works

1. The contract defines which costs are reimbursable (for example field labor, materials, equipment rental, subcontracts, permits) and which are not (often home-office overhead, which the fee is meant to cover).
2. The contractor tracks every cost against the job and bills monthly with backup: invoices, timesheets and subcontractor pay applications.
3. The owner or its representative reviews and audits the costs, then pays cost plus the agreed fee.
4. Changes in scope adjust the cost and, depending on the contract, the fee.

## Types of cost-plus contracts

| Type | How the fee works | Who carries the risk |
| --- | --- | --- |
| Cost plus fixed fee | A set dollar fee agreed at the start. It does not rise if costs rise, though it can be adjusted for scope changes. | Owner carries cost overruns; contractor's profit is capped. |
| Cost plus percentage | Fee is a percentage of the actual cost (for example cost + 15%). | Owner. The contractor earns more as costs rise, so there is little incentive to save. |
| Cost plus fee with a [guaranteed maximum price (GMP)](https://essential.construction/academy/glossary/guaranteed-maximum-price/) | Cost plus fee, but the total is capped. Savings below the cap are often shared. | Shared. The contractor pays costs above the GMP unless a change order raises it. |

The AIA publishes standard forms for both main versions: A102 (cost of the work plus a fee, with a GMP) and A103 (cost of the work plus a fee, without a GMP). AIA describes A103 as suited to large projects where the cost isn't fully known when construction starts.

US federal contracts handle this differently. The Federal Acquisition Regulation (FAR 16.102) prohibits the cost-plus-a-percentage-of-cost system, and FAR 16.306 notes that a cost-plus-fixed-fee contract gives the contractor "only a minimum incentive to control costs." Private owners can still use percentage fees.

## When to use a cost-plus contract

- The scope isn't fully designed, such as fast-track or design-build work.
- Renovations and repairs where hidden conditions make a fixed price a guess.
- Emergency or insurance restoration work that has to start before it can be priced.

## Pros and cons

|  | For the owner | For the contractor |
| --- | --- | --- |
| Pros | Work can start sooner; full cost transparency; no hidden risk premium in the price | Low risk of losing money; fee is protected |
| Cons | Final cost unknown at signing (unless there is a GMP); more admin and auditing | Detailed cost records required; costs can be disputed; profit is limited |

## Tips

- Write down exactly what counts as reimbursable cost, including markups on subcontracts and equipment rates.
- Agree how the fee changes (or doesn't) when scope changes.
- Track time and materials daily. Missing backup is the most common reason costs get rejected.

## Cost-plus contract templates

- [Cost Plus Fixed Fee Contract](https://essential.construction/files/business-operations/legal/cost-plus-fixed-fee-contracts/)
- [Cost Plus Fixed Percentage Contract](https://essential.construction/files/business-operations/legal/cost-plus-fixed-percentage-contracts/)
- [Time and Material Tracking Sheet](https://essential.construction/files/business-operations/finance/time-and-material-tracking-sheet/): keep the cost backup the owner will ask for
- [Construction Management Contract](https://essential.construction/files/business-operations/legal/construction-management-contract/)

## Related terms

- [Guaranteed Maximum Price (GMP)](https://essential.construction/academy/glossary/guaranteed-maximum-price/)
- [Contingency](https://essential.construction/academy/glossary/contingency/)
- [Change Order](https://essential.construction/academy/glossary/change-order/)
- [Schedule of Values](https://essential.construction/academy/glossary/schedule-of-values/)
- [Common types of construction contracts](https://essential.construction/academy/tutorials/common-types-of-construction-contracts-and-their-use/)

## Frequently asked questions

### What is a cost-plus contract in construction?

It is an agreement where the owner pays the contractor's actual project costs plus a fee for overhead and profit. The fee can be a fixed amount or a percentage of cost, and some versions cap the total with a guaranteed maximum price.

### What is a typical fee on a cost-plus contract?

There is no standard rate. The fee depends on project size, risk, market and how much overhead the contract lets the contractor bill as cost. Compare the fee and the reimbursable cost definitions together, not the percentage alone.

### Is cost-plus better than a fixed price?

It depends on how well the scope is defined. With complete drawings, a fixed price gives the owner more certainty. With unknowns, cost-plus avoids paying a large risk premium, but the owner takes on the risk of overruns.

### What is the difference between cost-plus and time and materials?

Both reimburse actual work. Time and materials usually bills labor at set hourly rates that already include overhead and profit, plus materials at cost or with a markup. Cost-plus reimburses actual cost and adds a separate fee.

### Can a cost-plus contract have a maximum price?

Yes. A cost-plus contract with a guaranteed maximum price caps the total the owner will pay. The contractor covers costs above the cap unless the scope changes through a change order.