# Lien Waiver

> A lien waiver gives up the right to file a mechanics lien, usually in exchange for payment. The four types of lien waivers, statutory forms and when to sign.

- URL: https://essential.construction/academy/glossary/lien-waiver/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-23

---

A **lien waiver** (or lien release) is a document in which a contractor, subcontractor or supplier gives up some or all of its right to file a mechanics lien on a property, usually in exchange for payment. Owners, general contractors and lenders collect lien waivers with each payment as proof that the people who did the work have been paid.

Lien laws are set by each US state (and in Canada by each province), so the forms, wording and rules differ from place to place. This page is a general explanation, not legal advice.

## Why lien waivers matter

In most US states, anyone who supplies labor or materials to improve private property and isn't paid can record a mechanics lien against that property, even if the owner has already paid the general contractor. That means an owner can end up paying twice. Lien waivers reduce this risk: each payment is matched by a waiver from the party being paid, and often from the subcontractors and suppliers below them.

## The four types of lien waivers

|  | Progress (partial) payment | Final payment |
| --- | --- | --- |
| **Conditional** | Waives lien rights for work through a stated date, but only once the stated payment is actually received | Waives all lien rights for the job, but only once final payment is actually received |
| **Unconditional** | Waives lien rights for work through a stated date, effective immediately, whether or not the money has cleared | Waives all lien rights for the job, effective immediately |

The safe practice for the party being paid is to send a **conditional** waiver with the pay request, and an **unconditional** waiver only after the payment has actually been received and cleared.

## How lien waivers are used in the payment cycle

1. The subcontractor submits its pay application with a conditional progress waiver.
2. The general contractor submits its own [pay application](https://essential.construction/academy/glossary/pay-application/) with its conditional waiver and its subs' waivers.
3. The owner or lender pays (often as part of a [draw request](https://essential.construction/academy/glossary/draw-request/)).
4. With the next pay application, each party provides an unconditional waiver for the previous payment received.
5. At the end of the job, final conditional and then final unconditional waivers are exchanged with final payment and release of [retainage](https://essential.construction/academy/glossary/retainage/).

## Statutory lien waiver forms

About a dozen states regulate the wording of lien waivers. California, for example, has four statutory forms in its Civil Code (sections 8132 to 8138), one for each type in the table above, and a waiver that doesn't substantially follow the statutory form may not be enforceable. Other states, such as Arizona, also prescribe forms, while Florida provides forms in its lien law. Most states don't regulate the form at all, so the wording you sign matters a great deal. Always check the rules for the state where the project is located.

## Lien waiver vs lien release vs payment bond

- **Lien waiver:** gives up the right to file a lien, usually before one has been filed.
- **Lien release:** often means removing a lien that has already been recorded, though many people use the terms interchangeably.
- **[Payment bond](https://essential.construction/academy/glossary/payment-bond/):** on public projects, where liens usually aren't available, the payment bond protects unpaid subs and suppliers instead.

## Tips for contractors and owners

- Never sign an unconditional waiver before the money is in your account.
- Read the "through date" and amount; make sure you're not waiving unpaid retainage, pending change orders or claims you intend to pursue.
- Owners and GCs: collect waivers from lower-tier subs and major suppliers, not just the first tier.
- Track waivers by payment so nothing is missing at final payment.
- Check whether your state requires a specific form or notarization.

## Templates for lien releases and payment

Many states require their own statutory waiver forms, so use those where they apply. For releases and final payment paperwork elsewhere, these templates help:

- [Release of Labour Lien Letter](https://essential.construction/files/business-operations/legal/release-of-labour-lien-letter/)
- [Final Payment Certificate](https://essential.construction/files/business-operations/finance/final-payment-certificate/)
- [Contractor Application for Progress Payment](https://essential.construction/files/business-operations/finance/contractor-application-for-progress-payment/)

## Related terms

- [Pay Application](https://essential.construction/academy/glossary/pay-application/)
- [Payment Bond](https://essential.construction/academy/glossary/payment-bond/)
- [Retainage](https://essential.construction/academy/glossary/retainage/)
- [Draw Request](https://essential.construction/academy/glossary/draw-request/)
- [Substantial Completion](https://essential.construction/academy/glossary/substantial-completion/)

## Frequently asked questions

### What is a lien waiver?

A lien waiver is a document in which a contractor, subcontractor or supplier gives up its right to file a mechanics lien on a property, fully or up to a certain date, usually in exchange for payment. It protects the owner from having to pay twice for the same work.

### What is the difference between a conditional and unconditional lien waiver?

A conditional waiver only takes effect once the stated payment is actually received. An unconditional waiver takes effect as soon as it is signed, whether or not payment arrives. That's why contractors send conditional waivers with invoices and unconditional ones only after being paid.

### Does a lien waiver need to be notarized?

In most states, no. A few states require notarization, and some owners or lenders ask for it anyway. Check the law in the project's state and the requirements in your contract or loan documents.

### When should I sign an unconditional lien waiver?

Only after you have actually received the payment it covers and the funds have cleared. Signing early means you may have given up your lien rights without being paid. If you're unsure, get advice from a construction lawyer in your state.