# Method Statement (RAMS)

> A method statement sets out step by step how a construction task will be done safely. What to include, method statement vs risk assessment, SWMS and JHA.

- URL: https://essential.construction/academy/glossary/method-statement/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-23

---

A **method statement** is a written, step-by-step description of how a specific task or activity will be carried out safely on a construction site: the sequence of work, the people, plant and materials involved, the hazards and the controls. It is usually prepared by the contractor doing the work and reviewed before the task starts.

The term is most common in the UK, Ireland, the Middle East and Commonwealth countries, where it is usually paired with a risk assessment as **RAMS** (risk assessment and method statement). Australia uses a safe work method statement (SWMS); the closest US equivalent is a [job hazard analysis](https://essential.construction/academy/glossary/job-hazard-analysis/) combined with a work plan.

## What's in a method statement?

- Scope of the task, location and drawings referenced
- Responsible persons, supervision and competency or training required
- Plant, equipment and materials
- Step-by-step sequence of work
- Hazards and control measures for each step (or a reference to the risk assessment)
- PPE and permits needed, such as a [hot work permit](https://essential.construction/academy/glossary/hot-work-permit/)
- Access, exclusion zones, and environmental controls
- Emergency and rescue arrangements
- Quality checks and inspection hold points
- Sign-off by the people doing the work

## Method statement vs risk assessment vs JHA

| Document | Answers | Where used |
| --- | --- | --- |
| Risk assessment | What could go wrong, how likely and how serious, and what controls are needed | Legal duty in the UK under the Management of Health and Safety at Work Regulations 1999 |
| Method statement | How exactly the work will be done, step by step, using those controls | UK, Ireland, Middle East, Asia |
| SWMS | The high-risk activities, hazards, controls and how they'll be implemented | Australia, required for high-risk construction work |
| JHA / JSA | Each job step, its hazards and controls | US and Canada |

## Is a method statement a legal requirement?

In the UK, a document called a "method statement" isn't generally required by law, but a suitable risk assessment is, and HSE identifies method statements as one way to plan and record how risks will be controlled. Some work, such as demolition, needs written arrangements before it starts, which are usually provided as a method statement. Main contractors and clients also commonly require RAMS before allowing work to start. In Australia, a SWMS is mandatory for the high-risk construction work activities listed in the WHS Regulations, such as work with a risk of a fall of more than 2 metres. Check the rules for your jurisdiction and contract.

## Who prepares it and when

The subcontractor or trade contractor doing the work writes the method statement, ideally with input from the supervisor and crew. The principal or main contractor reviews and accepts it before the task starts, and it is briefed to the workers, often in a [toolbox talk](https://essential.construction/academy/glossary/toolbox-talk/). It should be revised whenever the method, conditions or crew change.

## Tips for a useful method statement

- Write it for this site and this task. Generic, copied documents are the most common complaint from reviewers.
- Keep the steps in the order they'll actually be done.
- Name the controls specifically: which edge protection, which exclusion zone, which lifting gear.
- Keep it readable; workers should be able to follow it on site.
- Brief it and get signatures before work starts.

## Free and premium method statement templates

A template keeps the structure consistent, so reviewers can approve it quickly and the crew can find the steps that matter.

- [Project Method Statement](https://essential.construction/files/pre-construction/project-planning/project-method-statement/) template
- [Safe Work Method Statement Information Sheet](https://essential.construction/files/information/guides/safe-work-method-statement-information-sheet/) (free download)
- [Safety Activity Risk Assessment](https://essential.construction/files/construction/safety/safety-activity-risk-assessment/): pair it with your method statement

## Related terms

- [Job Hazard Analysis (JHA)](https://essential.construction/academy/glossary/job-hazard-analysis/)
- [Toolbox Talk](https://essential.construction/academy/glossary/toolbox-talk/)
- [Hot Work Permit](https://essential.construction/academy/glossary/hot-work-permit/)
- [Scaffold](https://essential.construction/academy/glossary/scaffold/)

## Frequently asked questions

### What is a method statement in construction?

It is a document that explains, step by step, how a particular task will be done safely: the sequence, people, equipment, hazards and controls. Contractors prepare it before starting work, and it is reviewed by the main contractor and briefed to the workers who will carry out the task.

### What is the difference between a method statement and a risk assessment?

A risk assessment identifies hazards, rates how likely and serious they are, and decides on controls. A method statement describes how the work will be carried out using those controls. In the UK they are usually submitted together as RAMS.

### What is the difference between an SOP and a method statement?

A standard operating procedure (SOP) describes how a routine task is always done, across many jobs. A method statement is written for a specific task on a specific site, taking account of that site's conditions, hazards and constraints.