# Punch List

> A punch list is the list of incomplete or defective work a contractor must fix before final completion. What goes on it, typical items, process and tips.

- URL: https://essential.construction/academy/glossary/punch-list/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-23

---

A **punch list** is a list of work that is incomplete, damaged or not built to the contract documents, prepared near the end of a construction project. The contractor must finish or correct every item before final completion and final payment. It is also called a deficiency list (Canada) or snag list (UK).

Punch items are usually small: a scratched door, missing cover plates, touch-up paint, a sticking window. Anything big enough to stop the owner using the building normally means the project is not yet at [substantial completion](https://essential.construction/academy/glossary/substantial-completion/).

## What goes on a punch list?

Each item should be specific enough that anyone can find it, fix it and check it off:

- Item number and location (building, floor, room or gridline)
- Description of the problem, ideally with a photo
- Responsible trade or subcontractor
- Date raised, target date and date closed
- Who verified the fix

### Typical punch list items

| Trade | Examples |
| --- | --- |
| Finishes | Paint touch-ups, drywall dings, grout gaps, damaged flooring, caulking missing |
| Doors and hardware | Doors that bind or don't latch, missing stops, closers out of adjustment |
| Mechanical and electrical | Missing cover plates and [access panels](https://essential.construction/academy/glossary/access-panel/), unlabeled panels, diffusers not aligned |
| Plumbing | Leaking traps, loose fixtures, missing escutcheons |
| Exterior and site | Sealant gaps, damaged sod, cleanup, line striping |

## How the punch list process works

1. **Contractor's own walk.** The general contractor and subcontractors walk each area and fix what they find before calling for an inspection. On AIA A201 projects, the contractor prepares and submits a list of items to be completed or corrected when it notifies the architect that the work is substantially complete.
2. **Design team inspection.** The architect, engineers and owner walk the work and add their items.
3. **Issue the list.** The combined list is distributed by trade, often in a punch list app or shared log.
4. **Fix and back-check.** Trades complete items, the contractor verifies, and the design team back-checks.
5. **Close out.** When every item is signed off, the project can move to final completion, final payment and release of [retainage](https://essential.construction/academy/glossary/retainage/).

## Punch list vs checklist vs deficiency log

| Document | When | Purpose |
| --- | --- | --- |
| Punch list | Near the end, at or before substantial completion | Lists remaining incomplete or defective work to finish before final completion |
| Quality checklist | Before, during and after each activity | Confirms each step was done right, so fewer items end up on the punch list |
| Deficiency log | Throughout the job | Tracks defects found at any stage; in Canada "deficiency list" is the usual name for the punch list itself |

## Who does what

The superintendent usually runs the punch process and the project manager tracks it against the schedule and billing. Subcontractors fix their own items. The architect or owner's representative inspects and verifies; on many contracts the architect also uses the list to decide whether to issue the certificate of substantial completion. The owner may hold back money for open items, so a long list can delay final payment.

## Tips for a shorter punch list

- Punch as you go: walk and close areas floor by floor instead of saving everything for the end.
- Protect finished work. Much of a typical punch list is damage from later trades.
- Write items so they can be closed: "Room 214: paint touch-up at door frame, north side," not "fix paint."
- Assign every item to one trade with a date.
- Photograph items when raised and when closed to avoid arguments at the back-check.
- Agree up front who pays when the responsible party is unclear (see [back charge](https://essential.construction/academy/glossary/back-charge/)).

## Free and premium punch list templates

A shared log with one line per item makes it easy to sort by trade, chase open items and show the owner exactly where closeout stands.

- [Deficiency Log Template](https://essential.construction/files/construction/quality/deficiency-log-template/) (free): a ready-to-use punch list and deficiency tracker
- [Simple Certificate of Completion Template](https://essential.construction/files/construction/quality/simple-certificate-of-completion-template/): for signing off once the list is closed
- [Turn Over Letters and Certificate of Completion](https://essential.construction/files/construction/turn-over-letters-and-certificate-of-completion/)

For the full closeout sequence, read [Construction Project Closeout](https://essential.construction/academy/tutorials/construction-project-closeout-everyones-favourite-part-of-the-project/).

## Related terms

- [Substantial Completion](https://essential.construction/academy/glossary/substantial-completion/)
- [Retainage](https://essential.construction/academy/glossary/retainage/)
- [Back Charge](https://essential.construction/academy/glossary/back-charge/)
- [As-Built Drawings](https://essential.construction/academy/glossary/as-built-drawings/)
- [O&M Manual](https://essential.construction/academy/glossary/om-manual/)

## Frequently asked questions

### What does punch list mean?

A punch list is the list of small remaining tasks and corrections a contractor must complete before a construction project is fully finished. It is created near the end of the job, usually during inspections around substantial completion, and every item must be signed off before final payment.

### Why is it called a punch list?

The usual explanation is that inspectors once punched a hole in the margin of the paper list next to each item, either when it was raised or when it was completed. The origin isn't certain, but the name stuck. It is also written "punchlist."

### What is the difference between a punch list and a checklist?

A checklist is used during the work to confirm each step is done correctly. A punch list is made near the end and records specific items that are still incomplete or defective. Good checklists during construction lead to shorter punch lists.

### Who creates the punch list?

The contractor usually prepares the first list from its own inspection, then the architect, engineers and owner add items during their walkthrough. The general contractor distributes the list to subcontractors and tracks it until every item is closed.

### Can the owner withhold payment for punch list items?

Often, yes. Many contracts let the owner withhold an amount for incomplete punch list items, sometimes a multiple of the estimated cost to finish them, until they are done. The exact rules depend on the contract and local law.