# Request for Quotation [RFQ]

> An RFQ asks suppliers or subs to price a defined item or scope. What to include, how to level quotes, RFQ vs RFP vs RFI, and whether a quote is binding.

- URL: https://essential.construction/academy/glossary/request-for-quotation/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-25

---

A **request for quotation (RFQ)** is a document asking suppliers or subcontractors for a price on a clearly defined item or scope: a material, a piece of equipment, a rental or a trade package. Each response is a quotation. RFQs are used when the requirement is known and price, lead time and terms are the main things being compared.

It is also called a request for quote or request for pricing. In some public procurement, "RFQ" can mean request for qualifications, which asks for experience rather than prices.

## What's on an RFQ?

- Project name, location and RFQ number
- Item or scope description, with spec sections, drawing references and quantities
- Required delivery date or work window
- Delivery terms, such as delivered to site or picked up, and who unloads
- What to include in the price (freight, taxes, submittals, warranty)
- Quote due date and how long the quote must stay valid
- Contact for questions and how to submit

## How the RFQ process works

1. Define the scope and quantities, usually from a [quantity takeoff](https://essential.construction/academy/glossary/quantity-takeoff/).
2. Send the same RFQ to at least two or three suppliers or subs so the quotes compare like for like.
3. Level the quotes: line them up in a comparison sheet and adjust for exclusions, freight and lead time.
4. Clarify gaps, then award with a purchase order or subcontract.

## RFQ vs RFP vs RFI

| Document | Asks for | Typical use |
| --- | --- | --- |
| RFQ | A price for a defined item or scope | Materials, equipment, rentals, small trade packages |
| [RFP](https://essential.construction/academy/glossary/request-for-proposal/) | Price plus approach, team, schedule and experience | Whole projects, design-build, consultants |
| [RFI](https://essential.construction/academy/tutorials/ultimate-guide-to-the-construction-rfi/) | Information or clarification, not a price | Questions about drawings and specs |

## Is a quotation binding?

It depends on the wording and your jurisdiction. In US federal purchasing, FAR 13.004 states that a quotation is not an offer, so the government's order is the offer and the contract forms when the supplier accepts it. In private work, a quote with firm terms may be treated as an offer. Either way, put the award in writing with a purchase order or subcontract that refers to the quote.

## Tips

- Ask every supplier to price the same quantities and spec, or the comparison is meaningless.
- Always ask for exclusions in writing. Freight, fuel surcharges and taxes are common gaps.
- Set a validity period (for example 30 or 60 days) when prices are volatile.
- Record lead times. The cheapest quote can cost more if it delays the schedule.

## RFQ templates

- [Request for Quotation (RFQ)](https://essential.construction/files/pre-construction/estimating/request-for-quotation-rfq/)
- [Construction Quotation Template](https://essential.construction/files/pre-construction/estimating/construction-quotation-template/): for subs and suppliers sending a quote
- [Construction Pricing Comparison](https://essential.construction/files/pre-construction/estimating/construction-pricing-comparison/): level quotes side by side
- [Purchase Order Price Comparison](https://essential.construction/files/business-operations/finance/purchase-order-price-comparison/)

## Related terms

- [Request for Proposal (RFP)](https://essential.construction/academy/glossary/request-for-proposal/)
- [Quantity Takeoff](https://essential.construction/academy/glossary/quantity-takeoff/)
- [Scope of Work](https://essential.construction/academy/glossary/scope-of-work/)
- [Submittal](https://essential.construction/academy/glossary/submittal/)

## Frequently asked questions

### What is an RFQ in construction?

It is a request sent to suppliers or subcontractors for a price on a defined item or scope, such as rebar, a crane rental or a small trade package. The responses are compared on price, lead time and terms.

### What is the difference between an RFQ and an RFP?

An RFQ asks only for a price on something already defined. An RFP asks for a proposal that also covers method, team, schedule and experience, and is judged on overall value.

### How many quotes should you get?

There is no universal number. Get enough to compare fairly; your company's procurement policy or the owner's contract may set a minimum, especially on public work.

### How long is a construction quote valid?

As long as the quote says. If it gives no validity date, ask for one in writing before you rely on the price in your bid.