# Retainage (Retention)

> Retainage is a percentage, often 5-10%, withheld from each progress payment until a construction job is done. How it works, limits, holdback and release.

- URL: https://essential.construction/academy/glossary/retainage/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-23

---

**Retainage** (also called retention) is a percentage of each progress payment that the owner withholds from the contractor, and the contractor from its subcontractors, until the work is complete. It gives the payer security that the work will be finished and defects corrected. Retainage is commonly 5% to 10%, released at or after completion.

Retainage rules are set by the contract and, on many projects, by state, provincial or federal law. This page is a general explanation, not legal or accounting advice.

## How retainage works

1. The contract sets the retainage rate, for example 10% of each progress payment.
2. Each month the contractor bills the full value of work completed on its [pay application](https://essential.construction/academy/glossary/pay-application/), and the retainage is deducted from the amount paid.
3. Retainage builds up over the job. Some contracts reduce the rate, for example to 5%, once the work is 50% complete and progressing well.
4. At [substantial completion](https://essential.construction/academy/glossary/substantial-completion/) the owner often releases most of it, keeping enough to cover open [punch list](https://essential.construction/academy/glossary/punch-list/) items.
5. The balance is paid with final payment, usually after closeout documents, warranties and final [lien waivers](https://essential.construction/academy/glossary/lien-waiver/) are received.

### Retainage example

|  | Amount |
| --- | --- |
| Work completed this month | $100,000 |
| Retainage at 10% | -$10,000 |
| Paid to contractor this month | $90,000 |
| Retainage held after five such months | $50,000 |

## Retainage limits and rules

- **US federal contracts:** retainage is not automatic. The FAR lets the contracting officer retain up to 10% of the approved estimate when progress is unsatisfactory, and says retained amounts must be paid promptly once the contract is complete.
- **US states:** many states cap retainage on public work, and some on private work, often at 5% or 10%, and set deadlines for releasing it. The rules vary widely, so check the statute for your project's state.
- **Canada:** provincial lien and prompt-payment acts require a statutory **holdback**, typically 10% of the value of work, retained by every payer down the chain and released after a set period once the lien period has expired.
- **UK and Australia:** "retention" is set by the contract, often in the range of 3% to 5%, with half commonly released at practical completion and the rest after the defects period.

## Retainage vs holdback vs withholding

| Term | Meaning |
| --- | --- |
| Retainage / retention | A contractual percentage held back from every payment until completion |
| Holdback (Canada) | A statutory amount held back to protect lien claimants, required by provincial law |
| Withholding / set-off | A specific amount held for a reason, such as defective work, a [back charge](https://essential.construction/academy/glossary/back-charge/) or missing paperwork |

## Who it affects

The owner holds retainage from the general contractor, and the general contractor holds it from subcontractors, usually at the same rate under a flow-down clause. Early trades such as sitework, foundations and structural steel can wait the longest for their retainage, because it is often not released until the whole project is complete, unless the contract allows line-item or early release. In accounting, it shows up as retainage receivable for the party owed it and retainage payable for the party holding it.

## Tips for getting retainage released

- Know the release trigger in your contract: substantial completion, final completion, completion of your scope, or a set time after completion.
- Track retainage by contract and line item on every pay app so the final number isn't a surprise.
- Submit closeout documents early: warranties, [as-builts](https://essential.construction/academy/glossary/as-built-drawings/), [O&M manuals](https://essential.construction/academy/glossary/om-manual/) and final waivers.
- Request early release for completed early trades if the contract allows it.
- Diarize statutory deadlines; prompt payment laws in many places set interest or penalties on late release.

## Templates for tracking retainage

A billing template that calculates retainage automatically every month keeps your running total accurate from the first invoice to the final release.

- [Construction Progress Billing Template](https://essential.construction/files/business-operations/finance/construction-progress-billing-template/): tracks billed, retained and paid by line item
- [Contractor Application for Progress Payment](https://essential.construction/files/business-operations/finance/contractor-application-for-progress-payment/)
- [Final Payment Certificate](https://essential.construction/files/business-operations/finance/final-payment-certificate/): for releasing the final retainage balance

See also [Construction Project Closeout](https://essential.construction/academy/tutorials/construction-project-closeout-everyones-favourite-part-of-the-project/).

## Related terms

- [Pay Application](https://essential.construction/academy/glossary/pay-application/)
- [Schedule of Values](https://essential.construction/academy/glossary/schedule-of-values/)
- [Substantial Completion](https://essential.construction/academy/glossary/substantial-completion/)
- [Lien Waiver](https://essential.construction/academy/glossary/lien-waiver/)
- [Progress Billing](https://essential.construction/academy/glossary/progress-billing/)

## Frequently asked questions

### What does retainage mean in construction?

Retainage is money held back from each progress payment, usually 5% to 10%, to make sure the contractor finishes the job and fixes defects. The contractor earns it as the work is done but is not paid it until completion or another release point set by the contract or law.

### What does 10% retention mean?

It means the payer keeps 10% of every amount billed. If a contractor bills $50,000 of completed work, it receives $45,000 and $5,000 is retained. The retained amounts add up over the project and are paid when the release conditions are met.

### Is retainage the same as retention?

Yes. "Retainage" is the usual US term and "retention" is used in the UK, Australia and elsewhere; both describe a percentage withheld from payments. In Canada, the similar statutory amount is called the holdback.

### When is retainage paid?

Usually at substantial or final completion, after the punch list is done and closeout documents and lien waivers are delivered. Some contracts release part at substantial completion or reduce the rate at 50% completion, and some state laws set deadlines for release.