# Shop Drawings

> Shop drawings are detailed drawings by a fabricator or contractor showing exactly how an item will be made and installed. What's on them and how review works.

- URL: https://essential.construction/academy/glossary/shop-drawings/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-23

---

**Shop drawings** are detailed drawings prepared by a contractor, subcontractor, fabricator or supplier that show exactly how a specific part of the work will be made and installed: dimensions, materials, connections, fastening and coordination with other trades. They are submitted to the architect or engineer for review before fabrication starts.

The design drawings show what the building should be. Shop drawings show how one piece of it will actually be built, often in far more detail than the designer ever draws.

## What's on a shop drawing?

- Plans, elevations, sections and details of the specific item
- Exact dimensions, tolerances and field-verified measurements
- Materials, grades, finishes and thicknesses
- Connections, anchors, welds and fasteners
- Piece marks and erection or installation sequence
- Interfaces with adjacent work and clearances
- References to the contract drawings and spec section, revision history and a title block
- Clouded deviations from the contract documents, if any

### Trades that typically produce shop drawings

| Trade | Examples |
| --- | --- |
| Structural steel and miscellaneous metals | Erection plans, connection details, [bent plates](https://essential.construction/academy/glossary/bent-plate/), embeds and [stud](https://essential.construction/academy/glossary/nelson-studs/) layouts |
| Concrete and [rebar](https://essential.construction/academy/glossary/rebar/) | Bar placing drawings and bending schedules, precast panel drawings, [post-tension](https://essential.construction/academy/glossary/post-tension/) layouts |
| Facade | [Curtain wall](https://essential.construction/academy/glossary/curtainwall/) elevations and anchor details, cladding panel layouts |
| Mechanical, electrical and fire protection | Coordinated [ductwork](https://essential.construction/academy/glossary/ductwork/) layouts, sprinkler drawings, electrical room layouts |
| Interiors | Millwork and casework, stairs and railings, ceilings, washroom partitions |

## Shop drawings vs construction drawings vs as-builts

|  | Construction (design) drawings | Shop drawings | [As-built drawings](https://essential.construction/academy/glossary/as-built-drawings/) |
| --- | --- | --- | --- |
| Prepared by | Architect and engineers | Contractor, fabricator or supplier | Contractor, from field records |
| Purpose | Show design intent and requirements | Show how a specific item will be fabricated and installed | Record what was actually built |
| Contract document? | Yes | No | No (closeout record) |
| When | Before bidding | After award, before fabrication | During construction and at closeout |

## The shop drawing review process

1. The fabricator prepares drawings from the contract documents and field measurements.
2. The general contractor checks and coordinates them with other trades and stamps them.
3. They are sent as a [submittal](https://essential.construction/academy/glossary/submittal/) with a [transmittal](https://essential.construction/academy/glossary/transmittal/).
4. The architect or engineer reviews for general conformance with the design and returns them stamped (approved, approved as noted, revise and resubmit, or rejected).
5. Once approved, the fabricator releases the work to the shop.

Under AIA A201, shop drawings are not contract documents, and the designer's approval does not relieve the contractor of meeting the contract documents unless a deviation was specifically pointed out and approved. Questions that come up while drawing should go through an [RFI](https://essential.construction/academy/tutorials/ultimate-guide-to-the-construction-rfi/), not be buried in the shop drawing.

## Tips

- Get long-lead shop drawings (steel, curtain wall, elevators, precast) started immediately after award.
- Field-verify dimensions before fabrication; "verify in field" notes on shop drawings are the contractor's responsibility.
- Cloud every deviation from the contract drawings so the reviewer can see it.
- Track every shop drawing and revision in a submittal log or drawing register.
- Only build from the latest approved revision.

## Templates for managing shop drawings

A register shows which revision is current and what is still waiting on review, which is the main cause of fabrication delays.

- [Submittal Cover Sheet](https://essential.construction/files/construction/administration/submittal-cover-sheet/): our best-selling form for sending shop drawings for review
- [Drawing Issue Register](https://essential.construction/files/design/drawing-issue-register/)
- [Drawing Register Template](https://essential.construction/files/design/drawing-register-template/)

For the full process, read [Construction Submittals: Types, Process, Log and Examples](https://essential.construction/academy/tutorials/managing-construction-submittals/).

## Related terms

- [Submittal](https://essential.construction/academy/glossary/submittal/)
- [Cut Sheet](https://essential.construction/academy/glossary/cut-sheet/)
- [As-Built Drawings](https://essential.construction/academy/glossary/as-built-drawings/)
- [Mockup](https://essential.construction/academy/glossary/mockup/)
- [Request for Information (RFI)](https://essential.construction/academy/tutorials/ultimate-guide-to-the-construction-rfi/)

## Frequently asked questions

### What is the difference between design drawings and shop drawings?

Design (construction) drawings are prepared by the architect and engineers to show what must be built and are part of the contract. Shop drawings are prepared by the contractor or fabricator to show exactly how a particular item will be made and installed, and are reviewed against the design drawings.

### Who prepares shop drawings?

The subcontractor, fabricator, manufacturer or supplier responsible for the item, often using in-house detailers or a specialist detailing firm. The general contractor reviews and coordinates them before submitting them to the design team.

### Are shop drawings contract documents?

Generally no. Under standard forms such as AIA A201, shop drawings are submittals that show how the contractor proposes to meet the contract documents. Approval does not change the contract unless a deviation was clearly identified and specifically approved, or a change order is issued.

### What are shop drawings in BIM?

On BIM projects, fabricators often model their work in 3D, coordinate it in the federated model to clear clashes, and then produce shop drawings and fabrication files directly from the model. The review process is the same, but coordination happens earlier.