# Site Instruction [SI]

> What a site instruction (supplemental instruction) is, what it contains, and how it differs from a change order or change directive on a construction job.

- URL: https://essential.construction/academy/glossary/site-instruction/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-03

---

A site instruction (SI) is a written instruction from the consultant (architect or engineer) or contract administrator to the contractor that clarifies the contract documents or directs how a minor item of work is to be done. In North America it is often called a supplemental instruction, and it is used to resolve minor issues so long as the change does not affect contract time or money.

## What a site instruction includes

- SI number, date, project name and who issued it
- The drawings, specification sections or RFI it relates to
- A clear description of the instruction, with sketches or marked-up drawings
- A statement that there is no change to contract price or time (in North American use)
- Signatures and distribution list

## Site instruction vs change order vs change directive

|  | Site instruction | Change order | Change directive |
| --- | --- | --- | --- |
| Purpose | Clarify or make a minor change | Formally change scope, price and/or time | Order a change before price or time is agreed |
| Price or time change? | No (North American use) | Yes, agreed | Yes, settled later |
| Contractor signs? | No, it is issued to them | Yes | Not required to proceed |

## Regional naming

In Canada, CCDC contracts use "supplemental instruction". In the US, the AIA form is Architect's Supplemental Instructions (ASI, G710). Under JCT contracts in the UK, instructions from the Architect or Contract Administrator can require a variation, which is then valued under the contract. In Australia, the Middle East and much of Asia, a "site instruction" may also instruct a variation, so read the contract.

## Tips for contractors

- If you believe an SI changes cost or time, notify the consultant in writing before doing the work, within the notice period in your contract.
- Log every SI in a register, issue it to affected subcontractors, and confirm verbal directions in writing.

## Related terms

- [Change Order](https://essential.construction/academy/glossary/change-order/)
- [Change Directive](https://essential.construction/academy/glossary/change-directive/)
- [CCN (Contemplated Change Notice)](https://essential.construction/academy/glossary/ccn/)

## Related templates and guides

- [Site Instruction Form](https://essential.construction/files/construction/administration/site-instruction-form/)
- [Site Instruction Template](https://essential.construction/files/construction/administration/site-instruction-template/)
- [Confirmation of Verbal Instruction](https://essential.construction/files/construction/administration/confirmation-of-verbal-instruction/)
- [RFI in Construction: What It Is, How to Write One](https://essential.construction/academy/tutorials/ultimate-guide-to-the-construction-rfi/)

## Frequently asked questions

### Does a site instruction change the contract price?

In North American practice, no. A site or supplemental instruction is meant for changes with no effect on price or time. If the contractor thinks it does affect them, they should give written notice before proceeding so it can be handled as a CCN, change order or change directive instead.

### What is the difference between an RFI and a site instruction?

An RFI is a question the contractor sends to the design team. A site instruction is a direction the consultant sends to the contractor. An RFI answer that clarifies or slightly alters the work is often formalized by issuing a site instruction.

### Who issues a site instruction?

The consultant or contract administrator, usually the architect or engineer of record, issues it to the general contractor. The GC then passes it to the affected subcontractors. Instructions from the owner directly should normally go through the consultant so the contract record stays complete.