# Value Engineering [VE]

> Value engineering (VE) finds lower-cost ways to deliver the same function and quality. How VE works, the six-phase job plan, examples and VE vs cost cutting.

- URL: https://essential.construction/academy/glossary/value-engineering/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-23

---

**Value engineering (VE)** is a structured review of a project's design, materials and methods to deliver the required functions at the lowest life-cycle cost, without reducing quality, performance or safety. In construction it usually means finding cheaper or faster alternatives that still meet the owner's needs.

The method was developed at General Electric in the late 1940s by engineer Lawrence Miles, originally under the name value analysis, and is now practised under standards from SAVE International, the value methodology society.

## How value engineering works

VE is built on a simple idea: value equals function divided by cost. You improve value by keeping the function and lowering the cost, or by improving the function for the same cost. A formal VE study follows a job plan, typically:

1. **Information:** understand the project, the owner's goals, the budget and constraints.
2. **Function analysis:** define what each element must do, in a verb and a noun ("support load," "keep water out"), and what that function costs.
3. **Creative:** brainstorm alternative ways to perform the high-cost functions, without judging ideas yet.
4. **Evaluation:** screen the ideas against cost, schedule, risk, quality and maintenance.
5. **Development:** work up the best ideas into proposals with costs, sketches and life-cycle analysis.
6. **Presentation:** present the proposals to the owner and design team for decisions, then implement the accepted ones.

On many projects VE is less formal: the contractor and design team review the estimate together and propose a list of savings items.

## Value engineering examples in construction

| Original design | VE proposal | Why it can work |
| --- | --- | --- |
| Cast-in-place concrete stair cores | Precast stairs | Faster, less [formwork](https://essential.construction/academy/glossary/formwork/), same function |
| Custom unitized [curtain wall](https://essential.construction/academy/glossary/curtainwall/) | Standard system profiles with more repetition | Lower fabrication cost, similar performance |
| Steel framing with many unique connection details | Standardized connections | Faster detailing and erection |
| High-end finish throughout | Premium finish in public areas only | Keeps the look where it matters |
| Oversized mechanical equipment | Right-sized units after load review | Lower first and operating costs |

## Value engineering vs cost cutting

|  | Value engineering | Cost cutting (scope reduction) |
| --- | --- | --- |
| Goal | Same function for less money | Less money, even if function or quality drops |
| Looks at | Life-cycle cost, including operation and maintenance | First cost only |
| Result | Owner gets what it needs | Owner gets less |

A lot of what gets called "VE" on site is really scope reduction. That isn't always wrong when a budget must be met, but owners should know which they are getting.

## When it happens and who is involved

VE delivers the most during design, when changes are cheap. Owners often run a VE workshop at schematic design or design development, led by a facilitator, with the design team, cost consultant and sometimes the contractor. On design-build, CM at-risk and [GMP](https://essential.construction/academy/glossary/guaranteed-maximum-price/) projects, the contractor typically proposes VE options during preconstruction. After the contract is signed, a contractor can still submit VE proposals; accepted ones go through a [change order](https://essential.construction/academy/glossary/change-order/). US federal contracts have formal value engineering change proposal (VECP) clauses in which the contractor shares in the savings; under the construction clause (FAR 52.248-3), the government's share on fixed-price contracts is 45%, leaving the rest to the contractor.

## Tips for VE that actually saves money

- Do it early. A VE idea at the shop drawing stage often costs more in redesign and delay than it saves.
- Price every idea including redesign fees, schedule impact and any knock-on effects on other trades.
- Check life-cycle cost and maintenance, not just first cost.
- Get the design team's sign-off on performance, code and warranty implications.
- Track accepted, rejected and pending ideas in one log so savings aren't double-counted.

## Value engineering templates

A VE log puts every proposal, its saving, its status and who approved it on one page, which is what owners and lenders want to see.

- [Construction Value Engineering Template](https://essential.construction/files/pre-construction/estimating/construction-value-engineering-template/)
- [Construction Estimate Comparison Template](https://essential.construction/files/pre-construction/estimating/construction-estimate-comparison-template/): compare the original and VE options side by side

Related reading: [Why Construction Projects Go Over Budget](https://essential.construction/academy/tutorials/why-construction-projects-go-over-budget/).

## Related terms

- [Guaranteed Maximum Price (GMP)](https://essential.construction/academy/glossary/guaranteed-maximum-price/)
- [Contingency](https://essential.construction/academy/glossary/contingency/)
- [Change Order](https://essential.construction/academy/glossary/change-order/)
- [Scope of Work](https://essential.construction/academy/glossary/scope-of-work/)
- [Proforma](https://essential.construction/academy/glossary/proforma/)

## Frequently asked questions

### What is an example of value engineering?

Replacing cast-in-place concrete stairs with precast stairs is a classic example: the stairs do the same job, but precast cuts formwork, labour and schedule time. Another is right-sizing mechanical equipment after a load review, which lowers both purchase and operating cost.

### What are the phases of value engineering?

A typical VE job plan has six phases: information, function analysis, creative (idea generation), evaluation, development and presentation. Some versions add preparation before and implementation or follow-up after. The phases are done in order, because each one feeds the next.

### Is value engineering just cost cutting?

It shouldn't be. True value engineering keeps the required function and quality while lowering life-cycle cost. Cutting scope or downgrading quality to hit a budget is cost reduction. Both happen on real projects, but they are different decisions with different consequences for the owner.

### Who does value engineering on a construction project?

Owners often hire a VE facilitator to run a workshop with the architect, engineers and cost consultant during design. Contractors, especially on design-build and CM at-risk projects, also propose VE ideas during preconstruction and after award.