# Common Types of Construction Contracts And Their Use

> The common types of construction contracts compared: lump sum, cost plus, unit price, GMP, design-build and CM at risk, and when to use each one.

- URL: https://essential.construction/academy/tutorials/common-types-of-construction-contracts-and-their-use/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-03

---

The most common **types of construction contracts** are lump sum (fixed price), unit price, cost-plus, guaranteed maximum price (GMP), time and materials, construction management, design-build and public-private partnership (P3) contracts. Each one splits cost, design and schedule risk differently between the owner and the contractor, so choosing the right one is one of the first big decisions on any project.

Construction projects are a conglomeration of various parties that all need to work together. Working together requires that each of the team members know their roles and responsibilities and what they are required to deliver. A construction contract is a tool that you can use to help outline these requirements.

### What exactly is a construction contract, how can it be used and what are the different types?

**A construction contract is a document that outlines the roles and responsibilities between two or more parties on a project. It is a legally binding document that the groups agree to at the start of a project and are held accountable to throughout.**

The contract can take many forms and formats. It can be complicated or simple and tailored to your project. No project is the same and no construction contract should be the same because of that. Whether it’s an industry standard form or your own, there are plenty of options for you.

**A construction contract should include information such as:**

- **Names of Companies or Individuals Involved**
- **Project Description and Details**
- **Cost of Work**
- **Inclusions and Exclusions within the work**
- **Requirements and responsibilities of each party**
- **Timeframe that the work is required to be completed (construction schedule)**
- **Staffing requirements**
- **Insurance Requirements**
- **Billing And Payment Requirements**
- **Procedures for Changes to the Contract**
- **Warranty and Closeout**
- **Dispute Resolution Processes**

## Construction Contract Types

As not every project is the same, there are various types of contracts between the owner and contractor which, depending upon which is chosen, can change your responsibilities drastically.

It helps to think about contract types in two ways. **Pricing (payment) types** describe how the contractor gets paid: lump sum, unit price, cost-plus, GMP and time and materials. **Delivery methods** describe how design and construction are organised: design-bid-build, construction management, design-build, P3 and integrated project delivery. A real contract combines the two, for example a construction manager at risk paid on a cost-plus basis with a GMP.

### Construction Contract Types Compared

| Contract type | How the price is set | Who carries cost overrun risk | Best suited to |
| --- | --- | --- | --- |
| Lump sum (stipulated sum / fixed price) | One fixed price for a defined scope | Contractor (owner pays for changes) | Complete designs, simple or competitively tendered projects |
| Unit price | Fixed rate per unit of work times measured quantities | Shared: contractor on rates, owner on quantities | Civil, roadwork and earthworks where quantities are uncertain |
| Cost-plus | Actual cost of the work plus a fixed or percentage fee | Owner | Unclear scope, fast-track, renovation and emergency work |
| Guaranteed maximum price (GMP) | Cost-plus with a ceiling price | Contractor above the GMP | Owners who want transparency and a cost cap |
| Time and materials | Hourly labour rates plus materials (often with a markup) | Owner (often limited by a not-to-exceed cap) | Small, undefined or repair work |
| Construction management | Fee for services (agency) or cost-plus/GMP (at risk) | Owner (agency) or CM up to the GMP (at risk) | Complex projects that need early contractor input |
| Design-build | Usually a lump sum or GMP for design and construction | Design-builder | Owners who want a single point of responsibility |
| P3 / design-build-finance-maintain | Long-term payments covering design, construction, financing and maintenance | Private partner (for agreed risks) | Large public infrastructure |

Below I’m going to walk you through the details of each as well as provide some real world examples. When utilizing each of these contracts it’s important to have someone knowledgeable in contract law prepare them - a lawyer or accountant should help review the nuances.

![construction contract template](https://essential.construction/academy/wp-content/uploads/2020/01/Contract-1-1024x573.png)

Purchase Our [Construction Contract Template](https://essential.construction/files/business-operations/legal/construction-contract-template-2/) Today and Save Time and Money on Your Projects.

## Lump Sum Contracts

A lump sum contract, also called a stipulated sum or fixed price contract, is one of the oldest and simplest types of construction contracts. This type is often used by governments and in simple residential construction.

A construction lump sum contract is based on creating a defined scope of work to be performed by a contractor and assigning a dollar value to that scope of work. If the work that is required to be performed is outside of the “scope of work” it is considered to be an extra to the contract, priced and approved through a [change order](https://essential.construction/files/construction/administration/change-order-template/).

Under a lump sum contract the consultants are typically engaged by the owner and the contractor falls under a separate contract with the owner. The contract is typically administered by the prime consultant. This arrangement is the traditional design-bid-build delivery method: the design is completed, the project is tendered, and the lowest compliant bidder usually wins.

I would recommend a lump sum contract type if you’re looking to get moving quickly on a project and have a complete design. These are great for usage on simple residential and commercial construction projects. Common standard forms include AIA A101 (Stipulated Sum) in the U.S. and CCDC 2 (Stipulated Price Contract) in Canada.

#### Lump Sum Construction Contract Example

As we move through the various contract types I’m going to keep the example consistent. For the examples I’ll be using an 11-storey office tower as the example building.

Utilizing a lump sum contract the owner would likely have engaged all of the consultants in advance and have a relatively complete design. Each component of the building would be outlined either in the contract documents or the scope of work.

The contract would be solely based on those documents and the scope of work. Meaning each door, wall, foundation type, mechanical unit, exterior wall system would be outlined in detail. Any change to, deviation or omission on those documents would be the responsibility of the owner to cover the costs.

#### Pros and Cons of Lump Sum Contracts

While this contract type seems risky, it’s been in use for hundreds of years and is still the benchmark that newer, more collaborative contract types are compared against. There are advantages and disadvantages to it which can include:

**PROS**

- **Defined Project -**the product that the owner is expecting to receive is defined in advance and known.
- **Competitive Value** - if the drawings are complete, having competitively tendered the project can create value as people try to beat each other for the project.
- **Widely Adopted -** there’s a familiarity within the industry. Contractors and owners are used to working under this type of agreement.

**CONS**

- **Design Risk** - if the contract documents aren’t perfect there’s an opportunity for the contractor to claim extras. This means missed details, changes in site conditions etc can all result in major cost changes.
- **Transparency -**the nature of a lump sum contract is that it is based on a whole and guaranteed number. The contractor is typically not required to provide as much information and cost breakdown.
- **Changes** - changes requested by the owner can have a bigger cost impact as the competitive nature of the tendering process can force contractors to try to make up money on these.

## Unit Price Contracts

A unit price contract breaks the work into measurable items, such as cubic yards of excavation, tonnes of asphalt or linear feet of pipe, and fixes a rate for each unit. The contractor is paid the agreed rate multiplied by the quantity actually installed and measured on site.

Unit price contracts are common in civil, road, utility and earthworks projects where the type of work is known but the final quantities are not. The owner carries the risk that quantities grow; the contractor carries the risk that its unit rates are too low. CCDC 4 is the Canadian standard form for unit price work.

#### Unit Price Contract Example

On the office tower, the owner might let the bulk excavation and shoring as a separate unit price contract because the depth of rock is not known until digging starts. The bid lists an estimated quantity of rock removal at a fixed rate per cubic yard, and the contractor is paid for the quantity surveyed each month.

**PROS**

- **Fair for uncertain quantities** - nobody has to gamble on quantities that cannot be known at tender.
- **Easy to compare bids** - rates are compared line by line.

**CONS**

- **Final cost unknown** - the owner does not know the final price until the work is measured.
- **Measurement disputes** - accurate, agreed measurement records are essential.

## Cost-Plus and Guaranteed Maximum Price (GMP) Contracts

A cost-plus contract pays the contractor the actual cost of the work (labour, materials, equipment and subcontracts) plus a fee for overhead and profit. The fee can be a fixed amount ([cost plus fixed fee](https://essential.construction/files/business-operations/legal/cost-plus-fixed-fee-contracts/)) or a percentage of cost. In the event that the overall project overruns the budget, the owner is responsible.

A [guaranteed maximum price](https://essential.construction/academy/glossary/guaranteed-maximum-price/) contract is a cost-plus contract with a ceiling. The contractor is still paid actual cost plus fee, but if costs exceed the GMP the contractor pays the difference. Many GMP contracts also share any savings below the GMP between owner and contractor. Common U.S. forms are AIA A102 (cost plus fee with a GMP) and A103 (without a GMP); in Canada, CCDC 3 is the cost-plus form.

As a former contractor a cost plus contract is really the holy grail of contract types with little risk!

#### Example of Cost-Plus and GMP Contracts

Using the office building example we noted above, a cost-plus contract is more fluid. Unlike the lump sum contract, it can start on day one before documents are complete.

An owner might provide a schematic design to a contractor and the contract can be written up on it based on the contractor’s experience. In the case of the office tower the contractor may initially sign a contract for an 11-storey office tower for a budget of $10 million. The contractor charges the owner based on the actual costs of the project including rates for overhead agreed to as part of the contract.

As the design progresses the owner may opt to take the guaranteed maximum price option - locking in a number and providing themselves with cost certainty.

## Construction Management Contracts

Construction management contracts are a newer alternative to the traditional lump sum approach. Unlike their lump sum counterparts they encourage a more collaborative approach to construction.

A [construction management](https://essential.construction/academy/tutorials/construction-management/) contract is an agreement between an owner and a contractor that allows the contractor to take a leadership role on the project, usually starting during design. The construction manager provides budgets and estimates based on the documents as they develop, fills in any blanks or risks with their experience, reviews constructability and coordination between documents, and then buys out and manages the trade work.

### "Construction Management Contracts Encourage a More Collaborative Approach to Building"

#### Two Types of Construction Management

There are two major forms of construction management contract:

- **CM agency (CM for services)** - the construction manager acts as the owner’s adviser for a fee. The owner holds the trade contracts directly and carries the cost risk. In Canada this is CCDC 5A.
- **CM at risk (CM for services and construction)** - the construction manager holds the trade contracts and is usually paid cost plus a fee, often with a GMP, so it carries cost risk above that price. Examples include CCDC 5B and AIA A133.

Once the budget is agreed, the construction manager engages subcontractors to perform the scopes and manages the owner’s money. Because the contractor has had the opportunity to build their own budget, and the team is relying on their experience to fill in the gaps, there can be less pressure on the contractor. A sample [construction management contract](https://essential.construction/files/business-operations/legal/construction-management-contract/) is a useful starting point when drafting one.

#### Pros and Cons of Construction Management

The nice thing about a construction management contract is that you’re relying on the contractor to be competent at what they do. This can have its pluses and minuses:

**PROS**

- **Flexibility -**a construction management contract allows you to bring on a contractor early on and start projects at different phases. It allows you to start construction before the drawings are complete.
- **Cost Certainty -**The GMP (Guaranteed Maximum Price) option provides the owner with cost certainty by relying on the [contractor to point out things wrong or missing in the design](https://essential.construction/academy/tutorials/construction-project-risk/).
- **Transparency -**all invoices and costs from subcontractors and suppliers are submitted through to the owner and consultants allowing for a full review.

**CONS**

- **Team Competency -**the project requires that the teams performing on the project are competent and good. The contractor is only as good as their experience meaning your estimate may be completely wrong.
- **Niche -**not every contractor and construction team is familiar with this construction contract type. Therefore it can be a challenge for people unfamiliar with the concept.

![construction management construction contract](https://essential.construction/academy/wp-content/uploads/2020/01/building-4349452_1920-1024x512.jpg)

## Time and Materials Contracts

A time and materials (T&M) contract pays agreed hourly rates for labour and equipment plus the cost of materials, usually with a markup. It is similar to cost-plus but simpler, and it is mostly used for small jobs, repairs, service work and extra work where the scope cannot be defined in advance.

Because the owner carries the risk of the job taking longer, T&M contracts often include a not-to-exceed amount and require daily time sheets signed by the owner’s representative.

## Design Build Contracts

We all know that one contractor that complains about how bad designers are. The great thing about design build construction contracts is that it puts the contractors in charge of the designers and consultants.

A design build contract is similar in nature to a construction management contract where the contractor is required to take a leadership role in the project. The major difference however, is that the contractor engages the consultants and provides a complete proposal to an owner, taking single-point responsibility for both design and construction.

Unlike construction management contracts and lump sum contracts the owner typically issues a request for proposal at the start of a project. Contractors and consultants partner up to create proposals featuring different designs and prices for the owner. The owner then selects a team to design and construct the building.

The request for proposal will contain some high level variables that the project teams must stay within, these can include price, design requirements, timeframes, etc. Standard forms include AIA A141 in the U.S., CCDC 14 in Canada, the JCT Design and Build Contract in the UK and the FIDIC Yellow Book internationally.

#### Examples of Design Build Contract

Utilizing the office tower example, an owner may have a vision for an office tower. They would start the process by issuing an RFP to a prequalified list of contractors.

The RFP may outline things like - we want an office tower for $10 million dollars with 11 floors and 100,000SF. The project needs to be completed within 4 years. It may then go on to provide further detail on the usage of the spaces, requirements for consultants and services that are to be provided.

Contractors then assemble design teams and submit proposals to the owner. The owner performs a detailed analysis on the bids verifying that the proposals meet the requirements of the project and awards based on that.

The contractor and consultants then partner up to complete the design, documents, permitting processes and ultimately deliver the project.

#### Pros and Cons of Design Build Construction Contract

Creating a team is one of the defining characteristics of design build contracts. If the project goes badly both the consultants and contractors will lose money. Therefore it is in everyone’s best interest for the project to go as planned.

That being said there are some pros and cons to the design build contract:

**PROS**

- **Teamwork** - the project team is [encouraged to work together](https://essential.construction/academy/tutorials/construction-industry-and-relationships/) to ensure the project is successful and profitable.
- **Management** - not every owner is experienced enough to run a project and make decisions early in the process. Having another team responsible for the details and pushing important decisions back to the owner can help an inexperienced owner.

**CONS**

- **Control** - this could be a pro or a con depending upon your role. As an owner you don’t control as much and especially with the design. As the contractor you can have more control which provides a benefit.

![design build finance and maintain construction contract](https://essential.construction/academy/wp-content/uploads/2020/01/road-4437939_1920-1024x575.jpg)

## Public Private Partnerships - Design, Build Finance and Maintain

One of the newer and more complex types of construction contracts is the Design Build Finance and Maintain (DBFM) model. Due to their complex nature these contracts are typically reserved for some of the largest projects run by governments.

A Design Build Finance and Maintain contract is very similar in nature to a design build contract with a few added complications. During the proposal process the contractor partners up with not just designers but lenders, equity investors and a facility manager as well.

At the completion of construction the facility manager takes over the building and runs it for a set number of years defined in the RFP. The private partner arranges the financing for design and construction, and the public owner repays it over the maintenance period, which can run for decades, typically through regular payments that depend on the facility being available and maintained to the agreed standard.

#### Examples of Design Build Finance Maintain Construction Contract

Utilizing the 11-storey office tower example, the process would work very similar to the design build construction contract example. The designers would be engaged by the contractor and they would collaborate to provide a design that works for the owner.

Because the construction team has a stake in the operation of the building often times the design process is much more involved. Owners create user groups which provide input throughout the design on how things like offices are laid out and spaces are used.

Once the construction team finishes building the office tower a facility manager takes over. They look after maintaining the building including janitorial staff and also maintain the building equipment (including mechanical and electrical equipment).

Finally, during this whole process the private partner’s lenders and investors are financing the work. They pay the design and construction costs up front, and the owner pays the private partner a set amount per month or year over the term of the agreement.

#### Pros and Cons of Public Private Partnerships

This is a bit of a sensitive issue. There are plenty of articles online that criticize them. The challenge is that due to their size, when there are issues that the public sees they are usually large. As an example an overrun on a two billion dollar project may be one hundred million dollars, however, in comparison to the size that's only an overrun of 5%.

Regardless, here's a rundown:

**PROS**

- **Comprehensive**- due to the design process the detail that goes into developing the project is typically more than most other projects.
- **Collaboration**- most times trades are brought on as partners early on in the process. This creates collaboration between designers and the people building it creating a more well coordinated building.
- **Usability -**As I noted above - user groups are often brought in during the design phase to comment on design. This creates a better space for the end user.

**CONS**

- **Complex -**due to their nature and size these projects are very complex. Only the biggest companies with the most resources can pursue them.
- **Costly Pursuit -**if you're unsuccessful in your bidding you can lose a lot of money. Due to their size these often take millions of dollars and resources to pursue.

## Other Construction Contract Types You May See

#### Design-Bid-Build

Design-bid-build is the traditional delivery method behind most lump sum contracts: the owner’s consultants complete the design, the project is [tendered](https://essential.construction/academy/tutorials/construction-tendering-the-basics/), and the successful bidder builds it. It gives a competitive price on a complete design but little contractor input during design.

#### Target Cost and Incentive Contracts

A target cost contract sets an agreed target price; the contractor is paid actual cost, and any overrun or saving against the target is shared between owner and contractor in agreed proportions. NEC4 Engineering and Construction Contract Options C and D are well-known target cost options.

#### Integrated Project Delivery (IPD)

IPD brings the owner, designers and key contractors into a single multi-party agreement that shares risk and reward based on overall project outcomes. In Canada, CCDC 30 is the standard IPD contract.

#### Subcontracts

Below the main contract, the general contractor or construction manager places subcontracts with trades and suppliers. These should pass down the relevant terms of the prime contract; a [subcontractor agreement template](https://essential.construction/files/business-operations/legal/subcontractor-agreement-template/) helps keep those terms consistent.

## Standard Forms of Construction Contract

Most projects start from an industry standard form rather than a blank page, then add supplementary conditions. The main families are:

| Standard form family | Where it is used | Examples |
| --- | --- | --- |
| AIA Contract Documents | United States | A101 (stipulated sum), A102 and A103 (cost of the work plus a fee, with and without a GMP), A133 (CM as constructor), A141 (design-build), A201 (general conditions) |
| ConsensusDocs | United States | Owner-contractor, design-build and CM agreements developed by a coalition of industry associations |
| CCDC | Canada | CCDC 2 (stipulated price), CCDC 3 (cost plus), CCDC 4 (unit price), CCDC 5A and 5B (construction management), CCDC 14 (design-build), CCDC 30 (IPD) |
| JCT | United Kingdom | Standard Building Contract, Design and Build Contract (2024 edition released April 2024), Minor Works |
| NEC4 | UK and international | Engineering and Construction Contract with main Options A to F (priced, target, cost reimbursable and management contracts) |
| FIDIC | International | Red Book (employer-designed construction), Yellow Book (plant and design-build), Silver Book (EPC/turnkey), 2017 editions |

Always check which edition of a standard form your project uses; several families, including CCDC and JCT, have issued new editions in the last few years.

## How to Choose the Right Type of Construction Contract

There is no single best contract. Work through these questions with your team and your lawyer:

- **How complete is the design?** A complete design suits lump sum; an early or evolving design suits cost-plus, GMP, CM or design-build.
- **How important is cost certainty?** Lump sum and GMP give the most price certainty; cost-plus and T&M give the least.
- **How important is speed?** CM, GMP and design-build let construction start before design is finished.
- **Are quantities known?** If not, consider unit price for those scopes.
- **How experienced is the owner?** Design-build and CM agency give less experienced owners more support; cost-plus requires an owner able to audit costs.
- **Who should carry design risk?** The owner keeps it under design-bid-build; it moves to the contractor under design-build and P3.
- **What does the market expect?** Using a familiar standard form usually means better bids and fewer disputes.

## Construction Contracts Matter

During the start up phase it can often be daunting to have the conversation with your owner about a contract. It can seem intimidating and inexperienced owners may think you're trying to take advantage.

For most industry veterans though a contract is a way to protect all of the people involved to ensure that if an issue arises there are rules and guidelines on how each party interacts. Having a contract on a construction project is one of the most fundamental requirements of any work.

## Frequently Asked Questions About Construction Contracts

#### What are the main types of construction contracts?

The main types are lump sum (fixed price), unit price, cost-plus, guaranteed maximum price (GMP), time and materials, construction management, design-build and public-private partnership contracts. The first five describe how the contractor is paid; the others describe how design and construction are delivered.

#### What is the most common construction contract?

The lump sum (stipulated sum or fixed price) contract, usually under a design-bid-build delivery, is still the most widely used, especially for public work and simpler projects with a complete design. Cost-plus with a GMP and design-build are common on larger or fast-track projects.

#### What is the difference between cost-plus and GMP contracts?

Both pay the contractor actual cost plus a fee. Under a plain cost-plus contract the owner pays all costs even if they exceed the estimate. Under a GMP contract the contractor pays any cost above the agreed maximum price, and savings below it are often shared.

#### What is a lump sum contract in construction?

A lump sum contract sets one fixed price for a clearly defined scope of work. The contractor carries the risk of its own costs, and the owner pays extra only for approved changes to the scope, usually through change orders.

#### What is the difference between NEC and JCT contracts?

Both are UK standard form families. JCT contracts are the traditional building contracts, such as the Standard Building Contract and Design and Build Contract. NEC4 contracts, such as the Engineering and Construction Contract, are written in plain language around collaborative project management and offer main options from priced contracts to target cost and cost reimbursable contracts.

#### Which construction contract type is best for the owner?

It depends on the project. Owners with a complete design and a need for price certainty usually choose lump sum. Owners who need to start early or want contractor input during design often choose CM at risk with a GMP or design-build. Always get legal advice before signing.

## Related Templates and Guides

- [Construction Contract Template](https://essential.construction/files/business-operations/legal/construction-contract-template-2/)
- [Cost Plus Fixed Fee Contracts](https://essential.construction/files/business-operations/legal/cost-plus-fixed-fee-contracts/)
- [Construction Management Contract](https://essential.construction/files/business-operations/legal/construction-management-contract/)
- [Construction Tendering – Everything You Need To Know](https://essential.construction/academy/tutorials/construction-tendering-the-basics/)

**What construction contract types have you worked under and what were their challenges? Feel free to share below in the comments.**