# How to Do a Field Level Hazard Assessment (FLHA) or Pre-Task Plan

> How to do a field level hazard assessment (FLHA) or pre-task plan: when it's needed, what Alberta law and OSHA say, 7 steps and a worked example.

- URL: https://essential.construction/academy/tutorials/field-level-hazard-assessment/
- Author: Kyle Parry (https://essential.construction/about-us/kyle-parry/, https://www.linkedin.com/in/kyleparry/) - Kyle Parry is the founder of Essential Construction. He has worked in construction for more than 20 years, leading projects across Canada for the country's largest contractors and developers.
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-27

---

**A field level hazard assessment (FLHA) is a short, written hazard check a crew does at the work location before starting a task, and again whenever conditions change. The crew walks the area, lists the job steps and hazards, picks controls, and everyone signs on. In the US the same tool is usually called a pre-task plan (PTP).**

This guide covers how an FLHA differs from a [job hazard analysis](https://essential.construction/academy/glossary/job-hazard-analysis/), when to do one, what Alberta law and OSHA guidance say about it, and how to fill one in step by step, with a worked example.

*Hazard assessment rules differ by province and state. Check your local regulations and site-specific requirements, and follow your company safety program where it sets a higher standard.*

## Key takeaways

- Do the FLHA **at the task, before work starts**, not in the trailer the day before.
- Redo it when anything changes: new task, new crew members, weather, equipment or work by another trade nearby.
- Pick controls in order: eliminate the hazard, then engineering controls, then administrative controls, then PPE.
- Every crew member reads and signs it. Anyone who joins later is briefed before starting.
- An FLHA checks today's conditions. It doesn't replace the JHA, safe work procedures or permits for high-risk work.

## Contents

- What is an FLHA?
- FLHA vs JHA vs toolbox talk
- When to do an FLHA
- Is an FLHA required?
- How to do an FLHA in 7 steps
- Example: a completed FLHA
- Common FLHA mistakes
- FAQs

## What is a field level hazard assessment (FLHA)?

An FLHA is the crew's own on-the-spot risk check. Where a company-level hazard assessment looks at a type of work in general, the FLHA looks at this task, in this spot, today. It catches the things a pre-written plan can't: a wet deck, an open floor edge another trade left, a delivery crane swinging overhead, a crew member who is new to the site.

Alberta's OHS Code Explanation Guide describes field level hazard assessments as on-the-spot assessments used where activities and conditions change often, such as construction sites, done at the start of the work day or when a new job starts. Alberta's hazard assessment handbook also calls them site-specific hazard assessments. In the US, contractors more often say pre-task plan, pre-task analysis or daily hazard assessment. The format varies, but the content is the same.

## FLHA vs JHA vs toolbox talk: what is the difference?

|  | FLHA / pre-task plan | Job hazard analysis (JHA) | Toolbox talk |
| --- | --- | --- | --- |
| Purpose | Check today's task and conditions | Set the standard steps, hazards and controls for a type of job | Train and remind the crew on one safety topic |
| Done by | The crew doing the work, led by the foreman | Supervisor or safety staff, with experienced workers | Foreman or supervisor |
| When | Every shift or task, and when conditions change | Before a type of work starts, reviewed periodically | Weekly or daily, depending on the site |
| Where | At the work location | Office or site, ahead of time | Usually a group meeting |
| Output | Signed card kept at the task | Written JHA used for planning and training | Attendance record |

Most sites use all three. The JHA sets the baseline, the [toolbox talk](https://essential.construction/academy/glossary/toolbox-talk/) keeps the crew sharp, and the FLHA checks that the planned controls fit what the crew is actually facing today.

## When should you do an FLHA?

- At the start of each shift, before the crew starts work
- Before each new task, or when the crew moves to a new work area
- When conditions change: weather, lighting, ground, traffic, or work by other trades nearby
- When the crew changes, or someone new or unfamiliar with the task joins
- After a near miss, incident or stop-work, before work restarts
- Alongside permits for high-risk work, such as [hot work](https://essential.construction/academy/glossary/hot-work-permit/), work at heights, excavation or [confined space](https://essential.construction/academy/glossary/confined-space/) entry

If the job takes all shift and nothing changes, one FLHA may be enough. If the crew moves around a lot, expect several cards a day.

## Is an FLHA required by law?

### Alberta

Alberta's Occupational Health and Safety Code, Part 2, is the clearest example in Canada. In the current consolidated text:

- Section 7(1): the employer must assess the work site and identify existing and potential hazards **before work begins**.
- Section 7(2) and (3): the results and the controls must be written in a report, and the date it was prepared or revised must be recorded.
- Section 7(4): the assessment must be repeated at reasonably practicable intervals, when a new work process is introduced, when a process or operation changes, and before significant additions or alterations to the work site.
- Section 8(1): the employer must involve affected workers in the assessment and in controlling or eliminating the hazards.
- Section 9: hazards must be eliminated or, if that isn't reasonably practicable, controlled, using engineering controls first, then administrative controls, then PPE.

The Code doesn't use the term FLHA, but on a changing construction site a signed FLHA is the practical way most employers show they met these duties at the task level.

### Other provinces

Every Canadian jurisdiction requires employers to identify and control hazards, but the wording, and whether a written task-level assessment is expected, differs. Check your provincial regulator and your prime contractor's site rules.

### United States

Federal OSHA has no standard that requires a form called an FLHA or pre-task plan. OSHA's [Recommended Practices for Safety and Health Programs](https://www.osha.gov/safety-management/hazard-identification) do call for regular workplace inspections with workers taking part, identifying hazards from non-routine tasks, and getting worker input before changing operations or equipment. Some standards also require specific checks before work, for example the confined spaces in construction standard requires a competent person to identify confined spaces before work begins (29 CFR 1926.1203(a)). Many general contractors and owners make a daily pre-task plan a contract or site requirement.

## How to do an FLHA in 7 steps

![Flow chart of the 7 FLHA steps: walk the area, plan the task, spot hazards, rate the risk, pick controls, sign on, and re-check when conditions change](https://essential.construction/academy/wp-content/uploads/sites/22/2026/11/field-level-hazard-assessment-flha-steps.png)

The FLHA is done at the work location, before the task starts, and redone when conditions change.

1. **Walk the work area.** Go to the actual spot. Look up, down and around: overhead lines and loads, floor openings and edges, ground and weather, lighting, access and exits, other trades and equipment moving nearby.
2. **Fill in the header.** Project, location, task, date and time, crew lead, any permit numbers, muster point and emergency contacts.
3. **Break the task into steps.** Three to eight main steps is usually right, for example: set up, cut, lift, install, clean up. Too few and hazards get missed; too many and nobody reads it.
4. **List the hazards for each step.** Include health hazards such as dust, noise and fumes, not just things that cause injuries right away. Include hazards created by other crews.
5. **Rate the risk.** Use your company's risk matrix, usually likelihood times severity. Rate each hazard before controls and again after controls, so the crew can see that the controls actually bring the risk down.
6. **Choose controls.** Work down the hierarchy: can you remove the hazard, change the method, put up a physical barrier or guard, use a procedure, permit or spotter, and finally PPE. Fix anything unsafe before work starts.
7. **Review and sign on.** The crew lead reads the card with the whole crew. Everyone signs. Keep the card at the task, where people can see it.

**During the shift:** if conditions change, stop, update the card, re-brief the crew and get new signatures if needed. At the end of the shift, note any hazards left for the next crew and hand the card to the supervisor for review.

Editable template

### Get the Field Level Hazard Assessment (FLHA) Form

A two-sided Word card with pre-start checks, hazard tick boxes, task steps with before and after risk ratings, PPE, crew sign-on and end-of-shift close-out.

[Download the template →](https://essential.construction/files/construction/safety/field-level-hazard-assessment-flha-form/?utm_source=academy&utm_medium=cta-template&utm_content=field-level-hazard-assessment)

## Example: what does a completed FLHA look like?

Task: core drilling three 4-inch holes through a suspended concrete slab on level 3 for plumbing sleeves. Two-person crew, other trades working on the floor below. This is an illustration of the level of detail to aim for, not a procedure for this task.

| Step | Hazard | Risk before | Controls | Risk after |
| --- | --- | --- | --- | --- |
| Set up | Floor below occupied: falling core or slurry | High | Barricade and sign the area below, spotter below during breakthrough | Low |
| Set up | Cords across walkway: trip | Medium | Route cords overhead or along walls, GFCI protection | Low |
| Scan and mark | Hitting rebar, post-tension tendons or buried conduit | High | Get the slab scanned and the locations approved before drilling | Low |
| Drill | Silica dust and slurry | Medium | Wet drilling with water control, wet vacuum, eye protection | Low |
| Drill | Bit binding, kickback | Medium | Anchor the rig to the slab, operator trained on the drill | Low |
| After breakthrough | Open hole: trips, falls of material | Medium | Cover and mark holes immediately with secured covers | Low |

Note how specific each control is. "Be careful" and "wear PPE" are not controls. If you work with [post-tensioned slabs](https://essential.construction/academy/glossary/post-tension/), scanning and approval before cutting are critical.

## Common FLHA mistakes

- **Filling it in before reaching the site**, or copying yesterday's card. The value is in looking at today's conditions.
- **Listing hazards with no controls**, or controls that are only PPE when a barrier or better method is possible.
- **Only the foreman knows what's on it.** Signatures without a briefing don't count for much.
- **Never updating it** when the weather turns, the crew moves or another trade starts work overhead.
- **No supervisor review.** Supervisors should check cards during the shift and use what they find, such as repeated hazards, in toolbox talks and JHA updates.

## Related templates and terms

- [Field Level Hazard Assessment (FLHA) Form](https://essential.construction/files/construction/safety/field-level-hazard-assessment-flha-form/)
- [Job Hazard Analysis Form](https://essential.construction/files/construction/safety/job-hazard-analysis-form/)
- [Hazard Identification and Assessment Program](https://essential.construction/files/construction/safety/hazard-identification-and-assessment-program/)
- [Safety Meeting Attendance Log](https://essential.construction/files/construction/safety/safety-meeting-attendance-log/)
- [Site Specific Safety Plan](https://essential.construction/files/construction/safety/site-specific-safety-plan-2/)

Related glossary terms: [Job Hazard Analysis](https://essential.construction/academy/glossary/job-hazard-analysis/), [Toolbox Talk](https://essential.construction/academy/glossary/toolbox-talk/), [Hot Work Permit](https://essential.construction/academy/glossary/hot-work-permit/), [Confined Space](https://essential.construction/academy/glossary/confined-space/), [Method Statement (RAMS)](https://essential.construction/academy/glossary/method-statement/).

## Frequently asked questions

### What does FLHA stand for?

Field level hazard assessment. It is a short written hazard check done by the crew at the work location before a task starts. In the US it is often called a pre-task plan.

### How often should an FLHA be done?

At least at the start of each shift or new task, and again whenever conditions, the crew or the work change. Your company or the prime contractor may set a stricter rule.

### Who fills out the FLHA?

The crew doing the work, usually led by the foreman or crew lead. Every worker on the task should take part and sign. A supervisor reviews it.

### Is an FLHA the same as a JHA?

No. A JHA is prepared ahead of time for a type of job and sets the standard steps and controls. An FLHA is done in the field for today's task and checks that those controls fit the actual conditions.

### How long should an FLHA take?

Long enough to walk the area and talk it through with the crew. For a routine task that is usually a few minutes. If the crew can't work out safe steps on the spot, the task needs a JHA or written procedure first.

*This guide is general information. Hazard assessment requirements differ by province and state. Check your local regulations, site-specific requirements and company safety program.*