I’m preparing a schedule for foundation work right now, hoping to confirm if I have the sequencing right:
1. Excavate for footings
2. Formwork for new footings
3. Rebar for new footings
4. Formwork for foundation walls
5. Reinforcement for foundation walls
6. Pour new foundation walls
Thanks for the help out with this one!
guillan Answered question February 16, 2022
Hey there! A few comments on your sequence:
- For your footings, depending upon the type, you may be able to excavate and pour against the soil. This may save you time but I’d check with your engineer.
- Formwork should be one side only, than reinforcement, than form second side (especially with the walls)
- You’ve missed stripping of the footings and foundation wall.
As always – check with other members of your team!
Hope that helps!
builderkp Answered question January 4, 2022
Confirmed Kyle’s comments above. Maybe just consider adding a line item for concrete curing so you can track when you can build on top of it.
guillan Answered question February 16, 2022