I’m preparing a schedule for foundation work right now, hoping to confirm if I have the sequencing right:

1. Excavate for footings
2. Formwork for new footings
3. Rebar for new footings

4. Formwork for foundation walls
5. Reinforcement for foundation walls
6. Pour new foundation walls

Thanks for the help out with this one!

guillan Answered question February 16, 2022