I’m preparing a schedule for foundation work right now, hoping to confirm if I have the sequencing right:
1. Excavate for footings
2. Formwork for new footings
3. Rebar for new footings
4. Formwork for foundation walls
5. Reinforcement for foundation walls
6. Pour new foundation walls
Thanks for the help out with this one!
guillan Answered question February 16, 2022
Confirmed Kyle’s comments above. Maybe just consider adding a line item for concrete curing so you can track when you can build on top of it.
guillan Answered question February 16, 2022