> Hi there - I work in the mid-west. We’re seeing some fairly significant lead time increases on things like electrical transformers and other high voltage gear. Anyone else experiencing this type of delay? What are…

- URL: https://essential.construction/exchange/question/lead-time-issues-on-electrical-gear/
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2023-04-20

---

Hi there - I work in the mid-west. We’re seeing some fairly significant lead time increases on things like electrical transformers and other high voltage gear. Anyone else experiencing this type of delay? What are you seeing?

## Answers

### Answer 1

10-12 weeks for panels

24-36 weeks for any large gear

some electronics are 36 weeks plus like meters.

### Answer 2

Similar to Guillan but we have 36 weeks +for anything high voltage.

### Answer 3

We’re still seeing some gear be extremely long lead but some of the lower voltage stuff has started to come back down to normal 6-8 week lead times.

### Answer 4

Things are getting better. 6-8 weeks for panels here.