# Change Order Log

> Construction change order log in Excel: track every change order, cost and time impact, status and approval in one place. $4.99, or free with a 14-day trial.

- URL: https://essential.construction/files/construction/administration/change-order-log/
- Publisher: Essential Construction (https://essential.construction/)
- Last updated: 2026-11-03
- Price: $4.99 USD (also included with Essential Construction membership)
- Categories: Administration, Finance
- Division: 01 - General
- File Type: Document
- Language: English

---

Organize every summary of work’s variation requirements with this Ready to fill Up Change Order Log.

This construction change order log gives you one place to record every change order on a project, from the first request to final approval. Use it to see what has been priced, what is still waiting on a signature, and how changes are affecting the contract value and schedule.

## What is a change order log?

A change order log is a running register of all change orders on a construction project. Each change gets its own line with a number, a short description, the date it was raised, its cost and time impact, and its current status. Project managers and contract administrators use the log to track approvals, keep the revised contract sum up to date, and give the owner and subcontractors a clear history of how the scope changed.

## When to use it

- When the owner, architect or engineer issues a change to the scope of work
- When a subcontractor submits a change order request (COR) that needs pricing and review
- When an RFI answer or site instruction adds cost or time
- Before monthly progress billing, to confirm which changes are approved and can be invoiced
- At project meetings, to review open changes and chase overdue approvals
- At closeout, to reconcile the final contract value

## What's included

The download is an Excel spreadsheet (.xlsx) set up as a ready-to-fill change order log. It is built to summarize each variation to the work on its own line, so you can sort, filter and total changes as the project moves along. Because it is a spreadsheet, you can add columns for your own cost codes, contract references or approval steps.

## How to fill it out

1. Enter the project name, number and contract details so the log can be shared without confusion.
2. Give every change a unique number as soon as it is raised, even if it is only a request.
3. Write a short, specific description and note the document that started it, such as an RFI, site instruction or drawing revision.
4. Record the date submitted, the proposed cost and any schedule impact in days.
5. Update the status as the change moves through pricing, review, approval or rejection.
6. Record the approved amount and approval date, then carry it into the revised contract total.
7. Review the log weekly and bring open items to your project meeting.

## Tips

- Log changes the day they come up. Late entries are the ones that get missed at billing.
- Keep pending and approved values separate so your cost forecast stays honest.
- Track time impacts as well as cost. Unrecorded delays are hard to claim later.

## Related templates and guides

- [Change Order Template](https://essential.construction/files/construction/administration/change-order-template/) – the form used to price and approve each individual change.
- [Change Order Requirement Form](https://essential.construction/files/construction/administration/change-order-requirement-form/) – capture the details of a requested change before it is priced.
- [RFI Log Template](https://essential.construction/files/construction/administration/rfi-log-template/) – track the questions that often lead to change orders.
- [Your Guide to Submitting a Construction Change Request](https://essential.construction/academy/tutorials/your-guide-to-submitting-a-construction-change-request/)
- [Change Order [CO] – glossary definition](https://essential.construction/academy/glossary/change-order/)

## Frequently asked questions

### What is a COR log in construction?

A COR log tracks change order requests. A COR is a contractor's or subcontractor's priced request for a change before it is approved. Many teams track requests and approved change orders in the same log, using a status column to show which requests have been accepted, rejected or are still under review.

### What is the difference between an RFI and a change order?

An RFI (request for information) is a question asking the design team to clarify the drawings or specifications. It does not change the contract by itself. A change order is a signed agreement that changes the scope, price or time of the contract. An RFI answer can lead to a change order if it adds work.

### What is the difference between a change order and an addendum?

An addendum changes the bid documents before the contract is signed, so every bidder prices the same scope. A change order changes the contract after it has been signed and work is underway. Addenda are issued during tendering; change orders are issued during construction.

### Can I track change orders in Excel?

Yes. A spreadsheet works well for most small and mid-size projects. Keep one row per change, use consistent status values, and total approved and pending amounts separately. This log is an Excel spreadsheet, so you can sort and filter by status, date or subcontractor.