For our mission critical deliveries we ask the subcontractors for tracking numbers immediately upon release of the material. We than take this tracking number and put it in a spreadsheet and our coordinator...

View Question
0 Votes

Similar to Rowena - falling objects is high for us. Electrical hazards was an issue last week.

View Question
0 Votes

10-12 weeks for panels 24-36 weeks for any large gear some electronics are 36 weeks plus like meters.

View Question
2 Votes Selected

I'd agree with the comments above - but would recommend you talk to your local building inspector. Each jurisdiction I've worked in has treated them differently so it's tough to give a specific one answer...

View Question