Hi there – I work in the mid-west. We’re seeing some fairly significant lead time increases on things like electrical transformers and other high voltage gear. Anyone else experiencing this type of delay? What are you seeing?
mikerv Answered question August 9, 2024
Similar to Guillan but we have 36 weeks +for anything high voltage.
builderkp Answered question April 23, 2023