Relationships (also called dependencies or logic links) connect the activities in a schedule and define which work must happen before or after other work. Without relationships, activities and a work breakdown structure are just an organized list. With them, scheduling software can calculate dates, float and the critical path. On a Gantt chart they are usually shown as arrows between bars.
The four types of relationships
| Type | Rule | Construction example |
|---|---|---|
| Finish-to-start (FS) | The successor cannot start until the predecessor finishes | Painting starts after drywall finishing is complete |
| Start-to-start (SS) | The successor cannot start until the predecessor starts | Taping starts two days after boarding starts (SS with a lag) |
| Finish-to-finish (FF) | The successor cannot finish until the predecessor finishes | Testing and balancing cannot finish until HVAC installation finishes |
| Start-to-finish (SF) | The successor cannot finish until the predecessor starts | Temporary heat cannot stop until the permanent heating system starts |
Finish-to-start is the default and by far the most common. Start-to-finish is rare and often a sign the logic should be redrawn.
Lag and lead
A lag adds waiting time to a relationship, such as curing time before stripping forms. A lead (negative lag) lets the successor overlap the predecessor. Use both sparingly and note the reason, because they hide work that is not shown as an activity.
Tips for good schedule logic
- Give every activity at least one predecessor and one successor, except the start and finish milestones. Activities with “open ends” make float meaningless.
- Drive dates with logic, not hard date constraints.
- Remove redundant links and check for loops.
Related terms
Related templates and guides
- Fundamentals of Construction Scheduling
- Lean Construction – Pull Planning Explained
- Simple Gantt Chart Template
Frequently asked questions
What are the four types of schedule relationships?
Finish-to-start (FS), start-to-start (SS), finish-to-finish (FF) and start-to-finish (SF). Each describes how the start or finish of one activity controls the start or finish of another. Most construction schedules are built mainly from FS links, with SS and FF used where work overlaps.
What is lag in a schedule relationship?
Lag is a time delay added to a relationship. For example, an FS link with a three-day lag means the successor starts three days after the predecessor finishes. Lag is often used for curing, drying or approval periods, but long or unexplained lags make a schedule harder to understand.
What is the difference between a predecessor and a successor?
A predecessor is the activity that controls another activity. A successor is the activity being controlled. In an FS link between drywall and painting, drywall is the predecessor and painting is the successor. One activity can have several of each.
Ask AI about this page: ChatGPT, Claude or PerplexityCopy as Markdown
