Change Directive [CD]

A change directive is a written instruction, issued by the owner or by the consultant on the owner’s behalf, that directs the contractor to carry ...
Kyle Parry
Kyle Parry
« Back to Glossary Index

A change directive is a written instruction, issued by the owner or by the consultant on the owner’s behalf, that directs the contractor to carry out a change in the work before price or time has been agreed. In the US it is usually called a construction change directive (CCD). It puts the contractor in a position where they must carry out the work, with pricing provided during or after the work.

When a change directive is used

  • The change is urgent and waiting for agreed pricing would delay the job.
  • The owner and contractor cannot agree on the cost or time of a proposed change.
  • A safety or code issue has to be fixed right away.

How it works

  1. The directive describes the change and states how it will be valued (for example lump sum, unit prices or cost plus a fee).
  2. The contractor proceeds with the work.
  3. The contractor tracks costs, normally on daily time-and-material sheets signed by the consultant or owner’s representative.
  4. Pricing and any time impact are submitted and reviewed.
  5. Once agreed, the directive is converted into a change order.

The AIA form in the US is G714, Construction Change Directive. Canadian CCDC 2 contracts call it a change directive.

Change directive vs change order

Change directive Change order
Price and time agreed? No, settled later Yes, before signing
Contractor must proceed? Yes, on receipt Once signed
Signed by Owner and consultant Owner and contractor (and architect on AIA)
End result Becomes a change order once agreed Final contract adjustment

Tips for contractors

  • Check the valuation method stated in the directive before starting.
  • Keep detailed daily records of labour, equipment and materials, and get them signed.
  • Flag schedule impact in writing straight away.
  • Log the directive in your change order log so it is not missed at billing.

Related terms

Related templates and guides

Frequently asked questions

Does a contractor have to follow a change directive?

Yes. Under standard contracts such as AIA A201 and CCDC 2, the contractor must proceed with the work described in a change directive even though price and time are not yet agreed. Disagreements over the final valuation are handled afterward through the contract’s change and dispute provisions.

Is a change directive the same as a change order?

No. A change order records an agreed change to scope, price and time. A change directive orders the work before that agreement. Once the parties agree on the adjustment, the change directive is converted into a change order.

How is the cost of a change directive determined?

The directive should state the method, typically a lump sum, agreed unit prices, or actual cost plus an agreed fee. Where cost-plus is used, the contractor’s daily records of labour, materials and equipment become the basis of the final change order.