A change directive is a written instruction, issued by the owner or by the consultant on the owner’s behalf, that directs the contractor to carry out a change in the work before price or time has been agreed. In the US it is usually called a construction change directive (CCD). It puts the contractor in a position where they must carry out the work, with pricing provided during or after the work.
When a change directive is used
- The change is urgent and waiting for agreed pricing would delay the job.
- The owner and contractor cannot agree on the cost or time of a proposed change.
- A safety or code issue has to be fixed right away.
How it works
- The directive describes the change and states how it will be valued (for example lump sum, unit prices or cost plus a fee).
- The contractor proceeds with the work.
- The contractor tracks costs, normally on daily time-and-material sheets signed by the consultant or owner’s representative.
- Pricing and any time impact are submitted and reviewed.
- Once agreed, the directive is converted into a change order.
The AIA form in the US is G714, Construction Change Directive. Canadian CCDC 2 contracts call it a change directive.
Change directive vs change order
| Change directive | Change order | |
|---|---|---|
| Price and time agreed? | No, settled later | Yes, before signing |
| Contractor must proceed? | Yes, on receipt | Once signed |
| Signed by | Owner and consultant | Owner and contractor (and architect on AIA) |
| End result | Becomes a change order once agreed | Final contract adjustment |
Tips for contractors
- Check the valuation method stated in the directive before starting.
- Keep detailed daily records of labour, equipment and materials, and get them signed.
- Flag schedule impact in writing straight away.
- Log the directive in your change order log so it is not missed at billing.
Related terms
Related templates and guides
- Change Order Log
- Confirmation of Verbal Instruction
- Common Types of Construction Contracts and Their Use
Frequently asked questions
Does a contractor have to follow a change directive?
Yes. Under standard contracts such as AIA A201 and CCDC 2, the contractor must proceed with the work described in a change directive even though price and time are not yet agreed. Disagreements over the final valuation are handled afterward through the contract’s change and dispute provisions.
Is a change directive the same as a change order?
No. A change order records an agreed change to scope, price and time. A change directive orders the work before that agreement. Once the parties agree on the adjustment, the change directive is converted into a change order.
How is the cost of a change directive determined?
The directive should state the method, typically a lump sum, agreed unit prices, or actual cost plus an agreed fee. Where cost-plus is used, the contractor’s daily records of labour, materials and equipment become the basis of the final change order.