Podium and PATH Bridges Progressing at CIBC SQUARE’s North Tower

[ad_1] With the North Tower having reached its prominent mechanical penthouse level, CIBC SQUARE is close to attaining its final shape ...
builderkp

[ad_1]

With the North Tower having reached its prominent mechanical penthouse level, CIBC SQUARE is close to attaining its final shape on the Downtown Toronto skyline. As glazing is applied to the upper storeys and crown over the coming months, the topped-off tower will rise about three and a half metres taller than its completed sibling to the south. Designed by WilkinsonEyre Architects and Adamson Associates Architects for Hines and Ivanhoé Cambridge, the project represents Toronto’s largest new office complex in about thirty years. 

CIBC South and North Towers on the Toronto skyline, January, 2025, image by UrbanToronto Forum contributor skycandy

Along with the new office space, the complex has brought a new GO Bus Terminal, new retail, a POPS that bridges over the rail corridor between the towers, and will be extending the pedestrian PATH system from the Financial Core to growing areas to the east through two new pedestrian bridges, one across Bay Street, and one across Yonge Street, both immediately north of the Union Station Rail Corridor.

The new PATH bridge from Union Station to CIBC SQUARE, image by UrbanToronto Forum contributor grammin

The Bay Street PATH bridge was completed first. In the September, 2024 image above, its structure has been completed and it is fully glazed. Faintly visible through the glazing the north wall of the platform area at Union Station can been seen, its windows forming a repeating pattern. The PATH will connect via the Front Street Level in Union Station to the second level at the CIBC SQUARE North Tower.

Below, in early January, 2025, we look southeast to the podium and where the Bay Street BATH bridge enters the complex. Some scaffolding along the podium has been removed since our last update, while white tarp now provides sheltered areas for installation of the lobby glazing. A projecting canopy extends above the Bay Street forecourt. 

The west elevation podium and connecting bridge to Union station, image by UrbanToronto Forum contributor Immensely Mental

 

Jumping back to October, 2024, this northeast-facing shot from over the exposed platforms at the east end of Union Station captures the podium as glazing was being applied to its upper floors. To the left, the recess is where public outdoor access will be gained to the enlarged POPS park deck that bridges over the tracks.

The CIBC SQUARE North Tower podium seen from the south in October, 2024, image by UrbanToronto Forum contributor mburrrrr

This southwest-facing December 10, 2024 image captures both podium from opposite it, and the Yonge Street PATH Bridge structure from above. Towering over it is the ongoing work on the North Tower and podium. Four storeys of curtain wall glazing panels have been installed on the southern volume of the podium, cantilevered over the rail corridor. Further glazing progress is visible along the upper right levels of the podium, where step-backs transition to the tower above. A scaffolding system, complete with stairs, is centralized within the podium volumes. 

The eastern volumes of the podium and Yonge Street pedestrian bridge, image by UrbanToronto Forum contributor Civdis

A month later, the Yonge Street PATH bridge was fully glazed in with large glass panels along its north and south sides. To the right, more glasz can be seen on the podium as well.

Glazing installed on the Yonge Street pedestrian bridge, image by UrbanToronto Forum contributor mburrrrr

The North Tower will stand 241.39m, slightly taller than the South Tower at 237.73m.

UrbanToronto will continue to follow progress on this development, but in the meantime, you can learn more about it from our Database file, linked below. If you’d like, you can join in on the conversation in the associated Project Forum thread or leave a comment in the space provided on this page.

* * *

UrbanToronto has a research service, UTPro, that provides comprehensive data on development projects in the Greater Golden Horseshoe — from proposal through to completion. We also offer Instant Reports, downloadable snapshots based on location, and a daily subscription newsletter, New Development Insider, that tracks projects from initial application.​​​

Related Companies:  Adamson Associates Architects, Bass Installation, BESI – Building Envelope Systems Installations, Doka Canada Ltd./Ltee, EllisDon, Grounded Engineering Inc., Hines, Isotherm Engineering Ltd., LiveRoof Ontario Inc, LRI Engineering Inc., Peter McCann Architectural Models Inc., Precise ParkLink, Rebar Enterprises Inc, RJC Engineers, RWDI Climate and Performance Engineering, SPX Cooling Technologies Inc., Trillium Architectural Products, Tulloch Engineering, Urban Strategies Inc., Walters Group