Critical Path

The critical path in construction is the longest sequence of dependent activities in the project schedule. It sets the shortest possible time to finish the ...
Kyle Parry
Kyle Parry
ms cp 1 - Critical Path « Back to Glossary Index

The critical path in construction is the longest sequence of dependent activities in the project schedule. It sets the shortest possible time to finish the job, and the activities on it have no float, so any delay to a critical activity delays project completion unless the time is recovered elsewhere.

On a Gantt chart the critical path is usually shown as red bars. As work progresses and activities finish early or late, the critical path can move to a different chain of activities, so it needs to be checked at every schedule update.

How the critical path works

Every activity has a duration and logic links to other activities (see schedule relationships). Scheduling software runs a forward pass to find each activity’s early start and finish, and a backward pass from the finish date to find its late start and finish. The difference is total float: how long an activity can slip without moving the end date. Activities with zero total float are critical.

Critical path example

A simple slab-on-grade building has these activities:

Activity Duration Follows
A. Excavation 5 days Start
B. Footings and foundation walls 4 days A
C. Underground plumbing 3 days A
D. Slab on grade 2 days B and C
E. Framing 10 days D

Path A-B-D-E takes 21 days. Path A-C-D-E takes 20 days. The longest path, A-B-D-E, is the critical path, and the project cannot finish in less than 21 days. Underground plumbing has 1 day of float: it can slip one day without delaying the job (it would then become critical), but a two-day slip would delay completion by a day.

How to manage the critical path on site

  • Build sound logic. Missing links or hard date constraints produce a false critical path.
  • Update regularly. Record actual starts, finishes and remaining durations, then recheck the path.
  • Watch near-critical work. Activities with only a few days of float can become critical quickly.
  • Use look-ahead schedules. Plan the next three to six weeks of critical work in detail with the trades.
  • Recover time deliberately. Add crews, work in parallel where it is safe, or resequence, and record why.
  • Document delays. Changes and delays to critical activities are central to extension-of-time claims, so follow the notice requirements in your contract.

Related terms

Related templates and guides

Frequently asked questions

How do you find the critical path in construction?

List the activities, their durations and their logic links, then calculate early and late dates through the network. Activities with zero total float form the critical path. Scheduling software does this automatically, but the result is only as good as the logic and durations you enter.

Can a project have more than one critical path?

Yes. If two or more chains of activities have the same longest duration, they are all critical. Near-critical paths, with only a few days of float, also deserve attention because a small delay can make them critical.

What is the difference between the critical path and the critical path method?

The critical path is the longest chain of dependent activities in a schedule. The critical path method (CPM) is the scheduling technique used to calculate it, by working out early and late start and finish dates and the float for every activity.

Does the critical path change during a project?

Often. Delays, faster progress, scope changes and resequencing can all change which activities drive completion. That is why the schedule should be updated regularly with actual progress, rather than relying on the critical path shown in the original baseline.