Temporary power is the electrical supply that runs a construction site, from tools, lighting and heaters to cranes, hoists and site offices, until the building’s permanent service is energized. It usually comes from a temporary utility service (a temporary power pole or pad-mounted transformer with a meter), a generator, or a sub-feed from an existing building.
If you’ve ever been on a project where the electrical breakers would be constantly tripping and lighting was at a minimum, don’t worry, you’re not alone. Temporary electrical systems are the heart of any construction site and if they go down so does your productivity. So what are temporary electrical systems and why are they so important?
Temporary electrical systems are infrastructure that is put in place to feed your jobsite until the permanent services can be brought in. Their purpose is to feed the jobsite so that the workers are able to perform regular tasks.
People often take things like charging their tools or having a working light for granted, but when they aren’t around it slows work down dramatically. We’re going to cover the following topics to ensure that you have a complete understanding of them on your jobsite:
- What are some examples of temporary electrical systems on a jobsite?
- Where temporary power comes from: utility service, generators and existing buildings
- Basic concepts for temporary electrical systems
- Who should be involved in preparing a temporary electrical system?
- The steps involved in getting a temporary electrical system in place on a jobsite
- Safety and code requirements for temporary power
- How long temporary power takes to set up and what drives the cost
- Challenges and professional tips for your project team
Building a project without a temporary network is like building a structure without concrete, it doesn’t happen. So let’s find the right way to do it!
What are some examples of temporary systems on a jobsite?
Electricity on a job makes things work, from the lights that keep spaces bright to the battery chargers for your drill. If it doesn’t exist it’s very difficult to build anything. Below are just a few examples of temporary electrical infrastructure on a jobsite:
- A temporary power pole with a meter and service panel supplied by the local utility
- A generator feeding the lights and power on a remote jobsite
- Installing a temporary breaker or panel to subfeed a construction site off of an existing service
- Temporary lighting stringers plugged into existing outlets in a building
- Solar panels feeding a temporary charging station for tools
- Temporary electrical panels installed throughout the building, floor by floor
As you can see, temporary systems range from very basic concepts to large networks feeding hundreds of pieces of equipment.
There’s a lot that goes into creating a temporary plan and network on your project. At no point should you be doing it alone. Input from all of your trades and co-workers is important to make sure that you’re not missing anything.
This article isn’t intended to explain everything about electrical design to you, but it is intended to give you a strong understanding of how to plan your temporary electrical network on your next project.
Where Temporary Power Comes From
The first big decision is the source. Most sites use one of the options below, and larger projects often combine them, for example a utility service for the main load and a generator for a remote laydown yard.
| Source | Best for | Watch out for |
|---|---|---|
| Temporary utility service (power pole or pad-mounted transformer with meter) | Most new-build sites where the utility has lines nearby, and projects lasting more than a few months | Utility lead times, the utility’s own construction standards for the pole, meter base and grounding, and an inspection before the utility will connect |
| Generator | Remote sites, early works before the utility connects, short-duration or high-peak loads, and backup | Fuel deliveries and storage, noise, refuelling and maintenance, exhaust (never run one indoors), and sizing for motor starting loads |
| Existing building service | Renovations, fit-outs and additions where the owner’s service has spare capacity | Available capacity, owner approval, metering or recharge of energy costs, and not tripping the owner’s live operations |
| Battery or solar units | Small loads such as tool charging, lighting towers, cameras and site signage | Limited capacity, so they supplement rather than replace a main source |
Whichever source you choose, apply early. Utilities need time to design, schedule and connect a temporary service, and that lead time can easily become the item that holds up your start on site.
Basic Electrical Concepts
Electricity is measured and discussed in Amps, Volts, and Ohms with each having a critical role to play. We won’t go into too much depth but we found a great analogy online:
Voltage is measured in volts, current is measured in amps and resistance is measured in ohms. A neat analogy to help understand these terms is a system of plumbing pipes. The voltage is equivalent to the water pressure, the current is equivalent to the flow rate, and the resistance is like the pipe size.
Often in construction you won’t hear much about resistance (that’s typically designed by an engineer) but you will hear people discuss equipment in volts and amps, and whether it needs single-phase or three-phase power.
For a full walkthrough on the concepts we’ve found this article to be great at explaining it.
In order to start your temporary electrical plan you’re going to need a number of pieces of information:
A schedule – your temporary power requirements are going to change throughout construction. What you need at start up might be more or less than you need later on in the project. The other question you need to ask yourself is how long will you be on temporary power for? Will you need to run new equipment off of it or will the new building power be up before you start commissioning? Not sure how to schedule? We can help.
Logistics Plan – consider how you are getting material up and down the building, where deliveries will be? What are the pieces of equipment you will need to perform different activities. Have a read through our article on construction start up for a better understanding of items you might need at start up.
Trade Input – what power will each of the trades need? A large floor grinder might need a dedicated three-phase supply at a higher voltage, where your fans might only need a 120V 15A circuit. Each piece of equipment needs to be reviewed as this will dictate what power you take to where.
There’s never such thing as having too much information when planning this type of work.
Who Should Be Involved in Planning Temporary Power?
Temporary power touches almost everyone on site, so build the plan with the people who will use it, install it and approve it:
- Superintendent and project manager – own the plan, the budget and the schedule for temporary services.
- Electrical contractor – designs and installs the temporary distribution, pulls the permit and maintains the system.
- Electrical engineer – checks larger services, generator sizing and anything feeding critical equipment.
- Utility – sets the requirements for the temporary service, meter and connection, and schedules the hook-up.
- Electrical inspector or authority having jurisdiction – inspects the installation before it is energized.
- Trades and equipment suppliers – provide the load and voltage of their equipment, from tower cranes and hoists to welders and heaters.
- Owner or facility manager – on renovations, approves any connection to the existing building service.
How to Plan Temporary Power, Step by Step
Once you have an understanding of the different concepts of electricity and the above information we recommend you grab a floor plan of your building and work through the steps below.
Step 1 – Build a Load List
Before you size anything, list every piece of equipment that will run on temporary power. For each item record the voltage, single or three phase, the current or kW rating from the nameplate, where it will be used and the dates it will be on site. Your electrician or engineer uses this list to size the service, the feeders and any generator, and to decide which loads can share a circuit. It is also the list you will go back to every time a new trade arrives.
Step 2 – Temporary Electrical: Feeding The Beast
Start by identifying the source of power for how you will be feeding the project site. If you’re in an existing building and can use the power from it, good start. If however, you’re in the middle of a field and need to bring power in to the project you may need a temporary utility service or a generator. In order to figure out the sizing of the source you’ll need to pull in the load list you and your trades prepared and add it all up, allowing for the fact that not everything runs at once.
Once the source has been determined it’s time to start feeding the job site. Larger companies have pre-fabricated temporary panels (often called spider boxes or temporary power distribution boxes) but if you’re a smaller outfit you’ll have to have your electrician make up some temporary panels. As a recommendation we suggest building panels with a disconnect connected to an electrical panel feeding a series of GFCI-protected outlets mounted to a backboard. Another suggestion would be to install these on wheels so that they can be easily pushed around the job.
These should be distributed around the jobsite as needed, the frequency of them will be dictated on how much activity there is in a specific area. For example a mechanical room that has a significant amount of demolition and welding would require much more power than an open office area that needs to have a ceiling, carpet and walls installed.
Mark all of your small locations down on the floor plan.
Step 3 – Temporary Electrical: The Heavy Lifting
Once you have the jobsite fed for small equipment with your temporary panels it’s time to identify the bigger load equipment. Some examples of larger equipment which may need to be independently fed are:
- Tower crane
- Welding machine
- Floor grinding equipment
- Concrete pump
- Sprayed fireproofing pump
- Elevators or hoist equipment
- Temporary electrical heaters
- Chipping guns
There are a lot more examples, but each of these will likely require an independent electrical feed.
Mark all of these down on your floor plan.
Step 4 – Bring On The Lights!
Lighting is important on a project and you don’t want to forget it. Not only is it a safety requirement but having more light also increases productivity for workers. We recommend keeping your lighting feeds separate from your construction power feeds. This way if your breakers trip for your panels it won’t put your building into darkness. In the US this is also a code point: the NEC does not allow construction-site receptacles on a branch circuit that supplies temporary lighting.
A big part of temporary lighting of a building is the actual fixtures you’ll be using. Everyone’s least favourite way of lighting a project is the classic light stringer. Always damaged, never safe and always in the way. Other options can include high bay light fixtures, LED temporary fixtures or fixtures such as wobble lights. Whatever you use, lamps for general lighting need guards to protect them from accidental contact and breakage.
Plan light levels as well as fixture locations. OSHA’s construction illumination rule (29 CFR 1926.56) sets minimums such as 5 foot-candles for general construction areas and indoor corridors and exitways, 3 foot-candles for areas like concrete placement, excavation, waste areas and access ways, 10 foot-candles for shops and mechanical and electrical rooms, and 30 foot-candles for first aid stations and offices. Treat these as the floor, not the target, for finishing work.
Mark all of the lighting locations down on a floor plan, and the panel locations you’ll use to feed them. How much area one lighting panel can serve depends on the fixtures, the circuit sizes and the layout, so let your electrician lay out the circuits rather than working to a rule of thumb.
Step 5 – Putting It All Together
Once you have your floor plan with the locations of each of the above start by laying them out on a riser diagram. The wiring to each of the pieces of equipment will be critical for your material orders. Add each piece of equipment to the drawing and the source, then start drawing a line between it and the panels.
At this point in the process you may need to bring in an engineer to help you with the design, many panels can likely be fed off of a single line. Make sure to have someone sign off on the overall strategy and design.
Once you have the final design it’s time to start installing, when you’re planning it you should be looking at your constraints. Things like elevators can limit the size of equipment you bring into a given space.
Step 6 – Install, Inspect and Energize
Make sure to hire a qualified electrical contractor to install all of the equipment on your project. The contractor normally takes out the electrical permit (in Ontario, files a notification of work with the Electrical Safety Authority), and the installation has to pass inspection by the authority having jurisdiction before the utility will connect a temporary service. There may be a maintenance requirement for your equipment (ie monthly inspections), make sure this is followed.
Safety and Code Requirements for Temporary Power
Temporary does not mean exempt. Temporary wiring is covered by the electrical code and by construction safety regulations, and it is inspected like permanent work. The main requirements to know are:
- Ground-fault protection. OSHA (29 CFR 1926.404) requires either GFCIs on all 120-volt, single-phase, 15- and 20-amp receptacle outlets on construction sites that are not part of the permanent wiring, or an assured equipment grounding conductor program. Article 590 of the National Electrical Code requires GFCI protection for personnel on 125-volt, single-phase 15-, 20- and 30-amp receptacles used for temporary power. Check which NEC edition your jurisdiction has adopted.
- Canada. Temporary wiring falls under Section 76 of the Canadian Electrical Code, which also requires GFCI protection on standard 15 A and 20 A receptacles on temporary installations. Check your provincial amendments.
- Assured equipment grounding conductor program. If you use one instead of GFCIs, it must be written and kept on site, run by a competent person, include a visual check of cords and plugs before each day’s use, and include recorded tests at intervals of no more than 3 months.
- Cords and cables. Extension cords for portable tools must be three-wire and rated for hard or extra-hard usage. Protect cords from damage, keep them off sharp edges and out of doorways and pinch points, and don’t lay branch-circuit conductors on the floor.
- Receptacles. Use grounding-type receptacles, and keep tool receptacles off the temporary lighting circuits.
- Generators. Run them outdoors, away from doors, windows and air intakes, because of carbon monoxide. Small portable generators (5 kW or less) with insulated circuit conductors are exempt from the OSHA GFCI rule, but GFCI-protected cords are still good practice.
- Isolation. Lock out and tag out temporary panels and feeders before anyone works on them, the same as permanent equipment.
- Removal. Temporary wiring has to be removed once construction is complete or its purpose is served.
Give everyone on site a quick refresher with a GFCI toolbox talk when the temporary system goes live, and again when it is extended.
Inspecting and Maintaining Temporary Power
A temporary system takes a beating, so build inspections into the site routine:
- Daily: look for damaged cords and plugs, missing panel covers, tripped GFCIs that have been bypassed and cords run through water.
- Weekly: walk the distribution with the electrician, test GFCIs with the test button and check generator fuel, oil and grounding. A generator checklist and an electrical panel board checklist make this quick.
- Whenever the layout changes: update the floor plan and riser diagram, and re-check loads before adding new equipment.
How Long Does Temporary Power Take and What Does It Cost?
The honest answer is that it depends on your utility and your site. A plug-in generator can be running the day it arrives. A temporary utility service needs a utility application, design, a permit, installation by your electrician, inspection and then the utility connection, and in busy areas that can take weeks to months. Call the utility as soon as you have a load estimate and put the connection date on your schedule as a milestone.
Cost varies widely by region, but these are the items that drive it, so make sure each one is covered in your budget:
- Utility connection and metering fees, and the energy you use
- Pole, transformer, meter base and service equipment (rented or bought)
- Distribution panels, spider boxes, cords and lighting
- Electrician labour to install, move, maintain and remove the system
- Generator rental, fuel and servicing if used
- Permits and inspections
- Temporary heat, which is often the largest electrical load in winter
Challenges and Professional Tips
- Nuisance tripping. Constant tripping usually means overloaded circuits, damaged cords or water in connections. Fix the cause, never bypass a GFCI.
- Winter loads. Electric heaters can overwhelm a service sized for tools and lights. Plan heat in your load list from the start, especially if you are working to a winter protection plan.
- Switching to permanent power. Using the building’s permanent service for construction needs owner approval and a clear agreement on who pays for energy and how equipment warranties are protected.
- Theft and vandalism. Copper cords and generators walk off sites. Lock panels and generators and secure the site.
- Overhead lines. Keep cranes, pumps and ladders clear of overhead power lines feeding the site.
Finally, remember that things change on a job site.
Don’t expect to install this and leave it the same the whole time. It will need to be modified as trades come on board and leave. Include some contingency in your plan for those inevitable surprises that will come up as you go.
Do you have any temporary electrical ideas for your jobsite that are creative? We’d be interested in hearing about them so feel free to share them below!
Frequently Asked Questions
What is temporary power on a construction site?
Temporary power is the electrical supply used to build the project before the permanent service is energized. It feeds tools, lighting, heaters, cranes, hoists and site offices, and it comes from a temporary utility service, a generator or an existing building.
Who provides temporary power for construction?
The general contractor usually plans it and carries the cost, a licensed electrical contractor designs and installs the distribution, and the local utility supplies and connects the temporary service once the installation passes inspection.
What is a temporary power pole?
A temporary power pole is a pole with a meter base, service disconnect and receptacles that the utility connects to its lines to supply a site. The utility sets the requirements for the pole, meter base and grounding, so get its construction standard before your electrician builds or rents one.
Do construction sites need GFCI protection?
Yes. In the US, OSHA requires GFCIs on 120-volt, single-phase 15- and 20-amp receptacles that are not part of the permanent wiring, unless an assured equipment grounding conductor program is used, and the NEC requires GFCI protection on temporary 125-volt 15-, 20- and 30-amp receptacles. Canada’s electrical code has similar requirements for temporary wiring.
Is a generator or a temporary utility service better?
For most projects lasting more than a few months a utility service is cheaper to run and quieter. Generators make sense for remote sites, early works before the utility connects, short jobs and backup for critical loads.
How much lighting does a construction site need?
OSHA’s minimum is 5 foot-candles for general construction areas, 3 foot-candles for areas such as excavations, waste areas and access ways, 10 foot-candles for shops and equipment rooms and 30 foot-candles for offices and first aid stations. Finishing trades usually need much more light than these minimums.
Related Templates and Guides
- Weekly Safety Meeting – GFCI
- Generator Construction Checklist
- Equipment Safety Checklist – Electrical Panel Board
- Electrical Cabling Construction Checklist
- 8 Important Items To Include in Your Winter Protection Plan
This guide is general information. Rules for contracts, payment and site safety differ by country, state and province. Check your contract and local regulations, and get professional advice where it matters.
Ask AI about this page: ChatGPT, Claude or PerplexityCopy as Markdown

