Hi there – I work in the mid-west. We’re seeing some fairly significant lead time increases on things like electrical transformers and other high voltage gear. Anyone else experiencing this type of delay? What are you seeing?
mikerv Answered question
10-12 weeks for panels
24-36 weeks for any large gear
some electronics are 36 weeks plus like meters.
Kyle Parry Selected answer as best