Hi there – I work in the mid-west. We’re seeing some fairly significant lead time increases on things like electrical transformers and other high voltage gear. Anyone else experiencing this type of delay? What are you seeing?
mikerv Answered question
10-12 weeks for panels
24-36 weeks for any large gear
some electronics are 36 weeks plus like meters.
builderkp Selected answer as best
We’re still seeing some gear be extremely long lead but some of the lower voltage stuff has started to come back down to normal 6-8 week lead times.
wayne grayson Answered question