Work permit formats and permit to work templates for controlling high-risk tasks on construction sites. Use them to authorize, brief and close out work such as hot work, excavation, scaffolding, crane setup and lifting, elevated platforms and after-hours work, with clear sign-offs for supervisors, safety officers and the crews doing the work.
A permit to work is a written system that confirms a specific job, in a specific place and time, has been assessed and that the controls are in place before work starts. A general permit covers routine but hazardous tasks; task-specific permits add checks for one hazard, such as fire watch and combustible clearance for hot work, or ground conditions, lift plans and exclusion zones for cranes.
How a permit to work is used
Request: the supervisor describes the task, location, duration and crew.
Assess: hazards and controls are listed, referring to the job hazard analysis.
Authorize: an authorized person checks the controls on site and signs.
Brief and display: the crew is briefed and the permit is kept at the work location.
Close out: the area is made safe, the permit is signed off and filed.
On construction sites the terms are used interchangeably for a written authorization to carry out hazardous work. Note that 'work permit' can also mean government employment authorization; the templates here are jobsite safety permits.
Who can issue a permit to work?
Only a person authorized under your site or company permit system, usually a supervisor or safety officer who understands the hazards and has checked the controls in the field. The permit holder and the issuer both sign before work starts.
How long is a permit to work valid?
Usually for a set period such as one shift, as written on the permit. If conditions change, the scope changes or the work stops and restarts, the permit should be reviewed and reissued.
When do I need a hot work permit?
Hot work such as welding, cutting and grinding is one of the most common permit-controlled activities. Your site rules, client, insurer or local fire code may require one, so check those requirements before work begins.