Back Charge (Backcharge)

A back charge (also written backcharge) in construction is a cost that a general contractor deducts from a subcontractor’s payment, or bills to it, for ...
Kyle Parry
Kyle Parry
« Back to Glossary Index

A back charge (also written backcharge) in construction is a cost that a general contractor deducts from a subcontractor’s payment, or bills to it, for work the general contractor had to do or pay for on the subcontractor’s behalf, such as cleanup, damage repair or fixing defective work. It is a contractual offset, not a fine.

Back charges flow the same way between an owner and a general contractor, and between a subcontractor and its own suppliers or sub-subcontractors.

Common reasons for back charges

Reason Example
Cleanup GC’s labourers clear a trade’s debris after it ignored cleanup notices
Damage to other work A trade cracks finished flooring or damages installed glazing
Defective or incomplete work Another crew is brought in to fix work the sub failed to correct
Delay or disruption Extra costs caused by a sub’s late work, if the subcontract allows recovery
Services provided Hoisting, scaffold, power or equipment the sub was supposed to supply
Safety or code violations Costs of correcting an unsafe condition the sub created

How a back charge should be handled

  1. Notify in writing before doing the work where possible, describing the problem and giving the subcontractor a chance to fix it within a set time, as most subcontracts require.
  2. If it isn’t fixed, do or arrange the work and record it: dates, crew, hours, materials, equipment and photos.
  3. Issue the back charge with the cost breakdown and backup, referencing the subcontract clause.
  4. Agree or dispute. The subcontractor accepts it, negotiates, or disputes it under the subcontract.
  5. Deduct the agreed amount from the next progress payment, retainage or final payment, or process it as a deductive change order.

Back charge vs change order vs chargeback

  • Back charge: reduces what a party is paid because someone else covered its costs.
  • Change order: a signed change to the contract scope, price or time.
  • Chargeback: in banking and retail, a reversed card payment. Unrelated to construction back charges, though the words are often confused in search.

Tips to avoid back charge disputes

  • Spell out the back charge procedure, notice period and markup in the subcontract.
  • Never back charge without prior written notice unless it’s a genuine emergency.
  • Back up every charge with time sheets, invoices and photos.
  • Issue back charges promptly, not as a surprise at final payment.
  • Subcontractors: respond in writing within the time allowed, or you may be deemed to accept the charge.

Whether a back charge is enforceable depends on the subcontract wording and local law; this page is general information only.

Templates for back charges and notices

A standard written notice gives the trade a fair chance to fix the problem first, and gives you the paper trail you’ll need if you have to charge for it.

Related terms

Frequently asked questions

What is a back charge in construction?

It is a deduction from a subcontractor’s payment, or a bill to it, for costs the general contractor incurred because of the subcontractor, for example cleanup, repairing damage, or correcting defective work the subcontractor didn’t fix after notice.

Is it back charge or backcharge?

Both spellings are used in construction, along with “back-charge.” They mean the same thing. Contracts and accounting systems usually pick one form, so just be consistent within your own subcontracts, logs and letters.

Can a general contractor back charge without notice?

Most subcontracts require written notice and a chance to correct before a back charge, except in emergencies. Charging without following the subcontract’s procedure makes the charge much easier to dispute. The exact rules depend on the subcontract and applicable law.