Payment Bond

A payment bond is a surety bond that guarantees a contractor will pay its subcontractors, laborers and material suppliers for work and materials on a ...
Kyle Parry
Kyle Parry
« Back to Glossary Index

A payment bond is a surety bond that guarantees a contractor will pay its subcontractors, laborers and material suppliers for work and materials on a project. If the contractor doesn’t pay, eligible claimants can claim against the bond and the surety pays valid claims, up to the bond amount.

Payment bonds are usually issued alongside a performance bond. In Canada the equivalent is often called a labour and material payment bond. This page is a general explanation, not legal advice; claim rights and deadlines depend on the bond, the contract and the law where the project is.

Why payment bonds exist

On private projects, unpaid subcontractors and suppliers can usually protect themselves with a mechanics lien on the property. Public property generally can’t be liened, so the law requires payment bonds instead. On US federal construction, the Miller Act requires a payment bond for the protection of all persons supplying labor and material; the FAR applies it to contracts over $150,000, normally in the full contract amount. Most states have similar “Little Miller Act” laws for state and local public work. Private owners and lenders also ask for payment bonds to keep liens off their projects.

How a payment bond claim works

  1. Check you’re covered. Bonds usually protect subcontractors and suppliers with a contract with the prime contractor, and often the next tier down. Under the Miller Act, coverage generally stops at second-tier subcontractors and suppliers.
  2. Give notice on time. Under the Miller Act, a claimant with no direct contract with the prime contractor must give written notice to the prime within 90 days after it last furnished labor or material. State laws and private bond forms set their own notice rules.
  3. Submit the claim to the surety with backup: contract, invoices, delivery records and statement of account.
  4. The surety investigates and pays valid claims, disputes them, or asks the contractor to resolve them.
  5. Sue if needed, within the deadline. Miller Act suits must be brought within one year after the last labor or material was supplied. Missing a deadline can lose the claim entirely.

Payment bond vs performance bond

Payment bond Performance bond
Guarantees Subs, laborers and suppliers get paid The work is completed per the contract
Who can claim Eligible subcontractors and suppliers The owner (obligee)
Replaces Lien rights on public work The owner’s need to find and fund a replacement contractor
Typical amount Usually 100% of the contract price Usually 100% of the contract price

Both protect the owner in the end: a payment bond keeps unpaid suppliers from stopping the job or clouding the title. See the full bid, performance and payment bond comparison on the performance bond page.

Tips for subcontractors and suppliers

  • Ask for a copy of the payment bond at the start of the job, before you deliver anything. Public owners must usually provide one on request.
  • Record your first and last day of work or delivery; claim deadlines run from them.
  • Send notices by a method you can prove (certified mail or as the bond requires).
  • Don’t sign an unconditional lien waiver or bond release until you’ve actually been paid.
  • Get legal advice early when a claim is large or disputed.

Related templates

Sureties issue their own bond forms, but these help with the paperwork around bonded and lien-protected work:

Related terms

Frequently asked questions

What is a payment bond in construction?

It is a surety bond, bought by the contractor, that guarantees subcontractors, laborers and suppliers will be paid for their work and materials on the project. If the contractor fails to pay, eligible claimants can recover from the surety up to the bond amount.

Is there a difference between a performance bond and a payment bond?

Yes. A performance bond protects the owner by guaranteeing the work will be completed. A payment bond protects subcontractors and suppliers by guaranteeing they will be paid. They are often issued together, for example on the AIA A312 form, but they are separate bonds.

When is a payment bond required?

On US federal construction contracts over the Miller Act threshold (currently $150,000 under the FAR), and on most state and local public projects under Little Miller Acts, with thresholds that vary by state. On private projects, only when the owner or lender requires one.

Who can make a claim on a payment bond?

Usually subcontractors and suppliers who contracted directly with the prime contractor, and often those one tier below them. Under the federal Miller Act, protection generally reaches second-tier claimants. Eligibility and notice rules vary by bond form and state law.