Progress billing is a billing method in which a contractor invoices the client in stages as the work is completed, usually monthly, instead of billing the full price at the end. Each bill covers the value of work done (often a percentage of each line item) since the last bill, less retainage and previous payments.
In construction, the document that does the progress billing on most commercial jobs is the pay application. On smaller jobs it may simply be a progress invoice.
How progress billing works
- Break the contract price into billable items, usually a schedule of values.
- At the end of each billing period, measure the percent complete of each item.
- Multiply each item’s value by its percent complete to get the total earned to date.
- Subtract retainage and amounts already billed to get the amount due this period.
- Submit with backup, get it approved, and get paid.
Quick example
On a $400,000 contract, the work is 35% complete at the end of month three. Earned to date is $140,000. Less 10% retainage ($14,000) and $84,000 previously paid, the month-three bill is $42,000.
Progress billing vs other billing methods
| Method | How you bill | Best for |
|---|---|---|
| Progress billing (percent complete) | Monthly, by the value of work completed on each line | Commercial and longer projects |
| Milestone billing | Fixed amounts when defined milestones are reached (foundation, framing, drywall) | Residential and smaller jobs |
| Time and materials | Actual hours and materials plus markup | Repairs, uncertain scope, change work |
| Lump sum on completion | One invoice at the end | Very short jobs |
“AIA billing” is progress billing using the AIA G702/G703 pay application forms.
Why it matters
Progress billing keeps cash flowing so the contractor isn’t financing the whole job, and lets the owner pay only for work actually in place. For accounting, the gap between what has been billed and what has been earned shows up as overbilling or underbilling on the contractor’s work-in-progress report, so accurate percentages matter to the books as well as to cash.
Tips
- Agree the billing method, period and cut-off date in the contract.
- Base percentages on measurable progress, not on cost spent.
- Bill change orders only once they’re approved.
- Send lien waivers with each bill if the owner or lender requires them.
Progress billing templates
A template that carries your line items, percent complete, retainage and previous billing from month to month means each bill takes minutes, not hours.
- Construction Progress Billing Template: our best-selling billing template
- Progress Billing Template: Electrical
- Construction Progress Billing Workflow
Related terms
Frequently asked questions
What is progress billing in construction?
It is billing the client in installments as work is completed, typically monthly, based on the percent complete of each part of the work. Each progress bill shows the value earned to date, less retainage and previous payments, to arrive at the amount due.
What is the difference between progress billing and milestone billing?
Progress billing charges for the percentage of work completed each period. Milestone billing charges set amounts when specific stages are reached, such as completing the foundation or framing. Milestone billing is simpler; progress billing tracks the actual work more closely.
What is a progress payment?
A progress payment is the payment the owner makes in response to a progress bill or pay application: a partial payment for work completed so far, less any retainage. Progress payments continue until final payment at the end of the project.