Schedule of Values [SOV]

A schedule of values (SOV) is an itemized breakdown of the contract price into the parts of the work, such as divisions, trades, areas or ...
Kyle Parry
Kyle Parry
« Back to Glossary Index

A schedule of values (SOV) is an itemized breakdown of the contract price into the parts of the work, such as divisions, trades, areas or phases, with a dollar value against each line. Agreed at the start of the job, it becomes the basis for every monthly pay application: the contractor bills the percent complete of each line.

On AIA A201 contracts with a stipulated sum or guaranteed maximum price, the contractor must submit a schedule of values allocating the entire contract sum before its first application for payment.

What’s in a schedule of values?

  • Line item number and description (often grouped by CSI MasterFormat division)
  • Scheduled value for each line, adding up exactly to the contract sum
  • Separate lines for general conditions, insurance, bonds and fee, if the contract allows
  • Allowances and contingency lines, if included in the contract
  • Approved change orders, added as new lines as the job goes on

Schedule of values example

Line Description Scheduled value % complete Billed to date
1 General conditions $120,000 40% $48,000
2 Sitework $180,000 90% $162,000
3 Concrete $350,000 60% $210,000
4 Structural steel $420,000 25% $105,000
5 Mechanical $510,000 10% $51,000
6 Electrical $420,000 10% $42,000
Total contract sum $2,000,000 $618,000

The monthly pay application carries these lines, adds materials stored, and deducts retainage and previous payments.

How a schedule of values is used

  1. The contractor prepares the SOV from its estimate and subcontract values after award.
  2. The architect, owner or lender reviews it. Reviewers look for front-loading and lines too large to measure progress against.
  3. Once accepted, it’s loaded into the pay application (on AIA projects, typically the G703 continuation sheet; the AIA does not publish a separate SOV form).
  4. Each month the contractor updates percent complete per line, and the reviewer checks it against work in place.
  5. Change orders are added as new lines so the original contract and changes stay visible.

Schedule of values vs other cost documents

Document Purpose
Schedule of values Breaks the contract price into billable lines for progress payments
Estimate The contractor’s internal build-up of costs to set the bid price
Budget / cost report Tracks actual cost against the budget, often by WBS or cost code
Bill of quantities A priced list of measured quantities, common in the UK and Commonwealth; used for valuing work rather than a lump-sum SOV

Who prepares it and when

The general contractor’s project manager or estimator prepares the SOV right after contract award, from the bid and subcontract values, and submits it before the first pay app. Subcontractors provide their own SOVs to the general contractor, which often rolls them up. Lenders on financed projects typically review it before the first draw request.

Tips for a good SOV

  • Don’t front-load. Overpricing early work to improve cash flow is easy to spot and can delay approval.
  • Make lines measurable. Split large trades by floor, area or phase, and separate labor from material where useful.
  • Match your subcontracts so you can bill subs’ progress cleanly.
  • Keep closeout lines (for example as-builts, O&M manuals, training) so the owner has a clear basis to release final payment.
  • Keep it current with change orders; never bury changes in existing lines.

Schedule of values templates

A billing template that carries your SOV lines month to month does the percent-complete and retainage math for you and keeps every pay app consistent.

Related terms

Frequently asked questions

What is a schedule of values in construction?

It is a list of the parts of the work with a dollar value assigned to each, adding up to the contract price. The owner and contractor use it to measure progress and calculate each monthly progress payment, so it is agreed before the first pay application.

Who prepares the schedule of values?

The contractor prepares it, usually the project manager or estimator, from the bid and subcontract values. The architect, owner or lender reviews it and can object to lines that look front-loaded or unmeasurable before it is used for billing.

Is a schedule of values the same as a G703?

Not exactly. The schedule of values is the breakdown itself. The AIA G703 Continuation Sheet is the form commonly used to present it each month, with columns for work completed, stored materials, percent complete and retainage.

What is front-loading a schedule of values?

Front-loading means assigning too much value to early work, such as mobilization or foundations, so the contractor is paid ahead of actual progress. It improves the contractor’s cash flow but shifts risk to the owner, which is why reviewers check SOVs carefully.