Submittal

A submittal in construction is a document, drawing, data sheet or physical sample the contractor sends to the design team for review before ordering, fabricating ...
Kyle Parry
Kyle Parry
« Back to Glossary Index

A submittal in construction is a document, drawing, data sheet or physical sample the contractor sends to the design team for review before ordering, fabricating or installing a product. Submittals show how the contractor intends to meet the specifications, so the architect or engineer can catch problems before the material reaches site.

The word is construction jargon for “something submitted.” Outside construction you would usually say submission; on a US jobsite, “submittal” is the standard term.

Types of submittals

Type What it is Example
Shop drawings Drawings prepared by the contractor, fabricator or supplier showing exactly how an item will be made and installed Steel connection details, curtain wall elevations, millwork
Product data Manufacturer literature: cut sheets, data sheets, performance charts, wiring diagrams Pump curves, door hardware sheets
Samples Physical pieces of the actual material for colour, finish or texture approval Brick, carpet, paint draw-downs, stone
Mockups Full-size built assemblies that set the quality standard A section of masonry wall or a typical hotel room
Informational and closeout submittals Certificates, test reports, calculations, warranties, O&M manuals and record drawings Mill certificates, fire-rating listings, warranty letters

How the submittal process works

  1. Build the submittal register. The contractor lists every submittal the specifications require, section by section, with due dates tied to the schedule and lead times.
  2. Prepare and check. The subcontractor or supplier prepares the package. The general contractor reviews it against the drawings and specs and stamps it before sending it on. Under AIA A201 the contractor’s submission represents that it has checked and coordinated the submittal.
  3. Send with a transmittal. A cover sheet or transmittal records the spec section, revision, date and what is attached.
  4. Design review. The architect and engineers review for general conformance with the design intent and return it with an action stamp.
  5. Distribute and release. Approved submittals go to the field and the supplier, and fabrication or ordering is released.

Common review stamps

  • Approved / No exceptions taken: proceed.
  • Approved as noted / Make corrections noted: proceed, incorporating the comments.
  • Revise and resubmit: fix and send again before proceeding.
  • Rejected / Not approved: the product or approach does not meet the requirements.

Wording varies by firm, so check the legend on the reviewer’s stamp.

Submittal vs RFI vs transmittal

Submittal RFI Transmittal
Purpose Shows what the contractor proposes to supply and install Asks the design team a question about the documents Cover record of what was sent, to whom and when
Typical sender Contractor (prepared by subs and suppliers) Contractor Anyone
Changes the contract? No. Submittals are not contract documents No, but the answer can lead to a change order No

Who is responsible

The specifications, usually Division 01 section 01 33 00 Submittal Procedures in CSI MasterFormat, say what is required and how. Subcontractors and suppliers prepare most submittals; the general contractor’s project engineer or project manager runs the register and checks each package; the architect or engineer of record reviews; the owner is copied on items such as finishes and samples. Under AIA A201, shop drawings, product data and samples are not contract documents, and reviewer approval does not relieve the contractor of meeting the contract unless a deviation was specifically called out and approved.

Tips to keep submittals moving

  • Start the register in the first weeks of the job and prioritize long-lead items such as switchgear, elevators, curtain wall and structural steel.
  • Never pass a sub’s package straight through. An unchecked submittal wastes a review cycle.
  • Highlight any deviation from the specs clearly; buried substitutions cause disputes later.
  • Allow the review time stated in the specs (often 10 to 14 days) plus resubmittal time in the schedule.
  • Don’t install from an unapproved submittal.

For a full walkthrough with log examples, read our guide to construction submittals: types, process, log and examples.

Free and premium submittal templates

A standard cover sheet and log means every package arrives complete and nothing sits forgotten in someone’s inbox.

Related terms

Frequently asked questions

What does submittal mean?

In construction, a submittal is anything the contractor sends to the architect or engineer for review before using it: shop drawings, product data, samples, test reports or certificates. The review confirms the proposed product or detail matches the design intent before money is spent on fabrication or installation.

Is it submittal or submission?

Both are correct English. “Submittal” is the standard term in US construction and engineering for documents sent for review under the specifications. “Submission” is the general word used in most other contexts and is more common in UK and Commonwealth usage.

What is the difference between an RFI and a submittal?

An RFI asks the design team a question when the drawings or specs are unclear or conflict. A submittal shows the design team what the contractor plans to supply or build so they can review it. RFIs clarify the design; submittals confirm the contractor’s proposal meets it.

How long does submittal review take?

The specifications usually set the review period, commonly about 10 to 14 days per cycle, and longer for complex items or when several consultants review. Build that time, plus a possible resubmittal, into the schedule before the item’s order date.