A request for quotation (RFQ) is a document asking suppliers or subcontractors for a price on a clearly defined item or scope: a material, a piece of equipment, a rental or a trade package. Each response is a quotation. RFQs are used when the requirement is known and price, lead time and terms are the main things being compared.
It is also called a request for quote or request for pricing. In some public procurement, “RFQ” can mean request for qualifications, which asks for experience rather than prices.
What’s on an RFQ?
- Project name, location and RFQ number
- Item or scope description, with spec sections, drawing references and quantities
- Required delivery date or work window
- Delivery terms, such as delivered to site or picked up, and who unloads
- What to include in the price (freight, taxes, submittals, warranty)
- Quote due date and how long the quote must stay valid
- Contact for questions and how to submit
How the RFQ process works
- Define the scope and quantities, usually from a quantity takeoff.
- Send the same RFQ to at least two or three suppliers or subs so the quotes compare like for like.
- Level the quotes: line them up in a comparison sheet and adjust for exclusions, freight and lead time.
- Clarify gaps, then award with a purchase order or subcontract.
RFQ vs RFP vs RFI
| Document | Asks for | Typical use |
|---|---|---|
| RFQ | A price for a defined item or scope | Materials, equipment, rentals, small trade packages |
| RFP | Price plus approach, team, schedule and experience | Whole projects, design-build, consultants |
| RFI | Information or clarification, not a price | Questions about drawings and specs |
Is a quotation binding?
It depends on the wording and your jurisdiction. In US federal purchasing, FAR 13.004 states that a quotation is not an offer, so the government’s order is the offer and the contract forms when the supplier accepts it. In private work, a quote with firm terms may be treated as an offer. Either way, put the award in writing with a purchase order or subcontract that refers to the quote.
Tips
- Ask every supplier to price the same quantities and spec, or the comparison is meaningless.
- Always ask for exclusions in writing. Freight, fuel surcharges and taxes are common gaps.
- Set a validity period (for example 30 or 60 days) when prices are volatile.
- Record lead times. The cheapest quote can cost more if it delays the schedule.
RFQ templates
- Request for Quotation (RFQ)
- Construction Quotation Template: for subs and suppliers sending a quote
- Construction Pricing Comparison: level quotes side by side
- Purchase Order Price Comparison
Related terms
Frequently asked questions
What is an RFQ in construction?
It is a request sent to suppliers or subcontractors for a price on a defined item or scope, such as rebar, a crane rental or a small trade package. The responses are compared on price, lead time and terms.
What is the difference between an RFQ and an RFP?
An RFQ asks only for a price on something already defined. An RFP asks for a proposal that also covers method, team, schedule and experience, and is judged on overall value.
How many quotes should you get?
There is no universal number. Get enough to compare fairly; your company’s procurement policy or the owner’s contract may set a minimum, especially on public work.
How long is a construction quote valid?
As long as the quote says. If it gives no validity date, ask for one in writing before you rely on the price in your bid.