Confirmation of Verbal Instruction [CVI]

A confirmation of verbal instruction (CVI) is a written record, sent by the contractor to the architect, engineer or owner’s representative, of an instruction that ...
Kyle Parry
Kyle Parry
« Back to Glossary Index

A confirmation of verbal instruction (CVI) is a written record, sent by the contractor to the architect, engineer or owner’s representative, of an instruction that was given verbally on site or by phone. It states what was said, by whom and when, so the instruction, and any cost or time it causes, is documented before the work goes ahead.

In construction, “CVI” almost always means this document. It is common on Canadian, UK and Commonwealth projects, and the same idea is used everywhere: if it isn’t written down, it is hard to get paid for.

What goes on a CVI?

  • CVI number, project and date
  • Who gave the instruction, who received it, and the date, time and place
  • The instruction, in as close to the actual words as possible
  • Drawings, details or locations affected
  • Whether the contractor considers it a change, with an initial note on cost and schedule impact
  • A request to confirm, or to respond within a set time if the record is wrong
  • Signature lines for the contractor and the consultant

How the CVI process works

  1. A consultant or owner’s rep gives a verbal instruction, often during a site walk.
  2. The contractor issues a CVI quickly, ideally the same day, and logs it.
  3. The consultant confirms, corrects or rejects it. Many teams then formalize it with a site instruction.
  4. If the instruction changes scope, price or time, it is priced and processed as a change order or change directive.

Some standard contracts spell this out. Under JCT contracts in the UK, an instruction given other than in writing has no immediate effect until it is confirmed in writing by the contract administrator or by the contractor, subject to the contract administrator not dissenting within the time the contract allows. Other contracts simply require all instructions to be in writing, which is exactly why CVIs exist.

CVI vs site instruction vs RFI

Document Written by Purpose
CVI Contractor Record an instruction already given verbally
Site instruction (SI) Architect or engineer Issue a written instruction or clarification
RFI Contractor Ask a question before acting

Tips

  • Send CVIs the same day. Memories fade and positions harden.
  • Be factual and specific; quote the instruction if you can.
  • Flag cost and time impact up front, even as “to be priced.”
  • Number and log every CVI and chase unanswered ones at the site meeting.
  • Check your contract: a CVI may not be enough on its own to authorize extra work.

CVI templates

A ready-made CVI form takes two minutes to fill in on site and turns a conversation into a record you can price.

Related terms

Frequently asked questions

What does CVI mean in construction?

CVI stands for confirmation of verbal instruction. It is a written note from the contractor to the consultant or owner confirming an instruction that was given verbally, so there is a record of what was asked, by whom and when, before the work proceeds.

Is a verbal instruction binding?

It depends on the contract. Many contracts say instructions must be in writing, and some, such as JCT forms, say a verbal instruction has no effect until confirmed in writing. Confirming it with a CVI is the safest way to protect your right to payment and time.

What is the difference between a CVI and a site instruction?

A CVI is written by the contractor to confirm an instruction that was given verbally. A site instruction is written by the architect or engineer to give an instruction directly. A CVI is often followed by a site instruction that formally confirms it.