Liquidated Damages [LDs]

Liquidated damages (LDs) are a fixed amount of money, or a formula, written into a contract that one party pays the other if it breaches ...
Kyle Parry
Kyle Parry
« Back to Glossary Index

Liquidated damages (LDs) are a fixed amount of money, or a formula, written into a contract that one party pays the other if it breaches a specific obligation. In construction they are almost always delay damages: a set amount per day or week that the contractor owes the owner for each day the project finishes late.

The amount is agreed when the contract is signed, so neither side has to prove the owner’s actual losses later. This page is a general explanation, not legal advice. Whether a clause is enforceable depends on the contract wording and the law where the project is.

How liquidated damages work on a construction project

  1. The owner estimates its losses from late completion before bidding: lost rent or sales, extended financing, extra consultant and supervision fees, temporary accommodation, and so on.
  2. The contract states a rate, for example “$2,500 per calendar day” for each day past the contract completion date, sometimes with a cap.
  3. The milestone is defined. LDs usually stop at substantial completion, not final completion, unless the contract says otherwise.
  4. Time extensions reduce exposure. Approved extensions for owner changes, excusable delays or weather move the completion date, so LDs only run on unexcused delay.
  5. The owner deducts LDs from progress payments, retainage or final payment, or claims them from the contractor (and potentially the performance bond).

Simple example

A contract sets LDs at $1,500 per day. The project reaches substantial completion 20 days after the adjusted completion date, and the contractor has no grounds for a further extension. The owner may withhold 20 x $1,500 = $30,000.

Are liquidated damages enforceable?

Generally yes, as long as they compensate rather than punish. Courts treat a clause that is really designed to punish as an unenforceable penalty. The tests differ by country:

  • United States: most states follow the Restatement (Second) of Contracts, section 356: the amount must be reasonable in light of the anticipated or actual loss and the difficulty of proving it. US federal contracts use LDs only where timely performance matters and damages would be hard to estimate, and the rate must be a reasonable forecast of just compensation (FAR 11.501).
  • United Kingdom: since Cavendish v Makdessi (2015), the question is whether the clause imposes a detriment out of all proportion to the innocent party’s legitimate interest.
  • Canada and Australia: broadly similar “genuine pre-estimate / not a penalty” principles apply, with local variations.

Liquidated vs actual (unliquidated) damages

Liquidated damages Actual (unliquidated) damages
Amount Fixed in the contract in advance Calculated after the breach
Proof of loss Not needed for each day of delay Must be proven with evidence
Certainty Both sides know the exposure at bid time Uncertain until settled or decided
Typical use Late completion of the works Defects, breaches without an LD clause, or where the LD clause fails

Many contracts make LDs the owner’s only remedy for delay, and many also contain a mutual waiver of consequential damages. How the two interact depends on the exact wording.

Who deals with LDs, and when

The owner and its lawyers set the rate before tender. Estimators should price the risk, and project managers should know the LD rate from day one, because it is what makes timely notices of delay and requests for extension so important. LDs flow down: general contractors often pass a share of LDs to the subcontractor that caused the delay, through their subcontract.

Practical tips for contractors and owners

  • Read the LD clause, the definition of completion and the extension-of-time procedure together.
  • Give written notice of every delay event within the contract’s time limit. Late notice can lose an extension.
  • Keep a current schedule showing the critical path so you can show what actually caused delay.
  • Owners: document how the rate was calculated. It is your best defence if the clause is challenged as a penalty.
  • Ask for a cap on LDs, commonly a percentage of the contract sum, if the rate is high.

Templates for managing delay

Most LD disputes are won or lost on paperwork. A standard notice gets delays on record quickly and in the right format.

Read more on contract types in Common Types of Construction Contracts.

Related terms

Frequently asked questions

What is an example of liquidated damages?

A building contract states that the contractor will pay the owner $2,000 for every calendar day the project is late past the agreed completion date. If the project finishes 15 days late with no approved extension, the owner can claim $30,000 without proving its actual losses.

Is liquidated damages a penalty?

It shouldn’t be. Liquidated damages are meant to compensate for likely losses that are hard to prove. If a court decides the amount is designed to punish, for example far above any realistic loss, it can treat the clause as an unenforceable penalty. The test depends on the governing law.

How are liquidated damages calculated in construction?

The owner estimates the daily cost of late completion when drafting the contract: lost income, financing, extra fees, temporary space and similar costs. That estimate becomes a daily or weekly rate. During the project, the owner multiplies the rate by the number of unexcused days of delay.

Can a contractor avoid liquidated damages?

A contractor reduces or avoids LDs by finishing on time or by securing time extensions for delays it did not cause, such as owner changes or excusable events. That requires timely written notice and schedule evidence under the contract. Some contractors also negotiate a cap or a grace period.

Ask AI about this page: ChatGPT, Claude or PerplexityCopy as Markdown

« Back to Glossary Index