As-built drawings are a revised set of construction drawings that show the project as it was actually built, including every change, relocation and field adjustment made during construction. The contractor marks them up as work progresses and hands them to the owner at closeout, so future maintenance, renovation and repairs start from accurate information.
They are also called as-builts, redlines or, once formally compiled, record drawings.
What as-built drawings show
- Changes from change orders, site instructions and RFI answers
- Actual locations and depths of underground utilities, sleeves and embedded items, dimensioned from fixed points
- Relocated walls, doors, equipment, access panels and fixtures
- Actual routing of concealed ductwork, piping and conduit
- Substituted products and approved deviations
- Elevations and grades where they differ from design
As-built vs record drawings vs shop drawings
| As-built drawings | Record drawings | Shop drawings | |
|---|---|---|---|
| Prepared by | Contractor and subcontractors | Often the architect or engineer, compiled from the contractor’s as-builts (depends on the contract) | Fabricator or subcontractor |
| When | Kept current throughout construction | At or after closeout | Before fabrication |
| Purpose | Capture field changes as they happen | Final, clean record for the owner | Show how an item will be made and installed |
The terms are used loosely: some owners and specifications use “as-built” and “record drawings” to mean the same thing. Check the project’s Division 01 specification, often section 01 78 39 Project Record Documents, for exactly what is required.
How as-builts are produced
- The contractor keeps a dedicated set of current drawings on site (paper or digital) for as-built markups only.
- Each trade marks up changes as they happen, typically in red, with dates and references to the RFI or change.
- The superintendent or project engineer reviews the set regularly. Many owners check it before approving the monthly pay application.
- At closeout, the marked-up set, or a CAD/BIM update of it, is submitted with other closeout documents such as the O&M manual and warranties.
- The design team or owner may convert it into formal record drawings.
Who is responsible?
Under most contracts the general contractor is responsible for maintaining and delivering as-builts, and it flows that responsibility down to subcontractors in their subcontracts. MEP and site utility trades usually carry the biggest share, because so much of their work ends up hidden. The owner uses them for facility management, and future designers rely on them for renovations.
Tips for accurate as-builts
- Record buried and concealed work before it is covered: photograph and dimension it from permanent reference points.
- Update weekly, not at the end of the job from memory.
- Note the reference (RFI number, change order, date) beside every change.
- Make it a standing item in the weekly site meeting and a condition of payment for trades.
- Agree the required format (PDF markups, CAD or BIM) at the start of the job.
Templates for tracking drawings
A drawing register shows which revision is current and which sheets still need as-built updates before closeout.
- Drawing Register Template
- Drawing Issue Register
- Turn Over Letters and Certificate of Completion: for handing over closeout documents
See Construction Project Closeout for the full handover list.
Related terms
Frequently asked questions
What is the difference between as-built and record drawings?
As-built drawings are the contractor’s marked-up set showing field changes, kept during construction. Record drawings are the final set, often compiled by the architect or engineer from those markups and issued to the owner. Many projects use the terms interchangeably, so the contract specifications decide.
Who is responsible for as-built drawings?
The general contractor is normally responsible for maintaining and submitting as-built drawings, with each subcontractor marking up its own work. The specifications set the format and timing, and delivery is usually a condition of final payment.
How much do as-built drawings cost?
On a new building, as-builts are part of the contract scope and are priced into the work. For an existing building with no drawings, a surveyor or architect can produce as-built (existing conditions) drawings; the cost depends on size, complexity and level of detail, so get quotes.
What is the difference between as-built and 100% design plans?
100% design drawings (issued for construction) show what the designers intended before work started. As-builts show what was actually built, including every change, relocation and substitution made during construction. On most projects the two differ in many places.
Ask AI about this page: ChatGPT, Claude or PerplexityCopy as Markdown
