A notice to proceed (NTP) is a written notice from the owner telling the contractor it may start work under the contract, usually on a stated date. It often sets the official start of the contract time, so the completion date, and any liquidated damages, are counted from it.
NTPs are standard on public projects and common on private ones, especially where permits, bonds, insurance or financing must be in place before work can begin.
What’s in a notice to proceed?
- Project name, contract number and parties
- The date the contractor may (or must) start work
- The contract time and resulting completion date, if the contract counts from the NTP
- Any limits: for example a limited NTP for design, procurement or site mobilization only
- Conditions still to be met, such as insurance certificates or permits
- Signature of the owner or contracting officer, and often an acknowledgement by the contractor
Where the NTP fits
- Bid or proposal accepted, then a notice of award or letter of intent.
- Contract signed; performance and payment bonds and insurance delivered.
- Notice to proceed issued.
- Contractor mobilizes; preconstruction meeting; work starts.
On US federal construction, the standard clause (FAR 52.211-10) requires the contractor to start work within a set number of calendar days after receiving the notice to proceed and to complete it within the stated period.
Notice to proceed vs notice of award vs notice of commencement
| Document | From / to | Purpose |
|---|---|---|
| Notice of award | Owner to winning bidder | Says the bid has been accepted; asks for contract signing, bonds and insurance |
| Notice to proceed | Owner to contractor | Authorizes work to start; often starts the contract clock |
| Limited notice to proceed (LNTP) | Owner to contractor | Authorizes only certain work, such as design or ordering long-lead items, with a cost cap |
| Notice of commencement | Owner, recorded publicly | In some states (for example Florida) a recorded lien-law document, not a start instruction |
Tips
- Don’t mobilize or order materials before the NTP unless you have a written limited NTP or other authorization. You may not be paid if the project stalls.
- Check whether contract time runs from the contract date or the NTP date, and diarize the completion date.
- If the NTP is late, give written notice; a delayed NTP can affect your price and schedule.
- Use the period between award and NTP to finish submittals, the baseline schedule and the safety plan.
Notice to proceed templates
A clear NTP letter fixes the start date in writing, which is the date everything else in the contract schedule is measured from.
- Notice to Proceed template
- Notice of Award
- Construction Startup Checklist: everything to line up before day one
See also Seven Steps to Construction Startup.
Related terms
Frequently asked questions
What is a notice to proceed in construction?
It is the owner’s written authorization for the contractor to begin work, usually on a stated date. On many contracts the NTP date starts the contract time, so it fixes when the project must be completed and when liquidated damages could begin.
What is a limited notice to proceed?
A limited notice to proceed (LNTP) authorizes only part of the work, such as design, mobilization or ordering long-lead equipment, usually with a cap on spending, before the full contract or financing is finalized. A full NTP follows later.
Can a contractor start work without a notice to proceed?
It can, but it is risky. If the contract requires an NTP, work done before it may not be paid for, insurance and bonds may not yet be in force, and the start date may be disputed. Get written authorization first.