Stop Work Order [SWO]

A stop work order is a written direction to halt all or part of the work on a construction project until a problem is resolved. ...
Kyle Parry
Kyle Parry
« Back to Glossary Index

A stop work order is a written direction to halt all or part of the work on a construction project until a problem is resolved. It can come from a building department (for example, work without a permit), from the owner under the contract, or from a safety regulator or the site’s own safety team.

What happens next, including who pays for the delay, depends on who issued it and why. This page is a general explanation, not legal advice.

Types of stop work orders

Issued by Common reasons How it’s lifted
Building department or code official No permit or expired permit, work outside the approved plans, failed inspections, unsafe conditions, unlicensed contractor Obtain the permit or approval, correct the violation, pay any fees or fines, pass re-inspection
Owner or contracting officer (contract stop work order) Funding, design changes, disputes, owner convenience, or contractor non-compliance Owner cancels the order or the contract procedure runs its course
Safety regulator Imminent danger to workers Hazard corrected and verified by the regulator
Contractor or site safety team (“stop work authority”) Any worker sees an unsafe condition Supervisor reviews, hazard controlled, work restarts

Contract stop work orders on federal projects

US federal contracts often include the FAR stop-work order clause (52.242-15). Under it, the contractor must stop the covered work immediately and take reasonable steps to minimize costs. The order lasts 90 days unless extended by agreement, after which the contracting officer must cancel it or terminate the work. If the order is cancelled or expires, the contractor resumes work and may be entitled to an equitable adjustment in time and price, but must assert that right within 30 days after the stoppage ends. Private contracts such as AIA A201 have their own clauses for owner-ordered suspension, so read your contract.

Regulatory stop work orders

  • Federal OSHA inspectors cannot shut a site down themselves. For an imminent danger, they inform employers and workers and can recommend that OSHA ask a federal court to restrain the work (OSH Act section 13).
  • Canadian provinces give inspectors direct power. In Ontario, for example, a Ministry of Labour inspector can issue a stop work order under section 57 of the Occupational Health and Safety Act.
  • Local building officials in most US jurisdictions can post a stop work order on the site under the adopted building code. Continuing work after one is posted can lead to fines or further enforcement.

What to do when you receive a stop work order

  1. Stop the affected work and make the area safe. Don’t remove a posted order.
  2. Read exactly what is covered: the whole site or one activity.
  3. Notify the owner, design team, subcontractors and your surety or insurer as the contract requires.
  4. Record the date and time, photograph the site and the order, and start tracking costs and delay separately.
  5. Fix the cause (permit, correction, hazard) and request re-inspection or cancellation in writing.
  6. Give written notice of any claim for time or money within the contract’s deadlines.

Stop work order templates

A written stop work notice makes the instruction clear on site and creates the record you’ll need for any later time or cost discussion.

Related terms

Frequently asked questions

Can a contractor issue a stop work order?

A general contractor can direct its subcontractors to stop work under their subcontracts, and many companies give every worker “stop work authority” for safety. A contractor can’t issue a regulatory stop work order, and stopping its own work against the owner usually requires a contractual right, such as non-payment provisions.

What happens if I get a stop work order?

Stop the covered work, make the site safe, and find out exactly what caused the order. Correct the issue, such as getting a permit or fixing the violation, then request re-inspection or cancellation. Track all delay and costs and give contractual notices promptly.

How long does a stop work order last?

Until the issuer lifts it. A building department order lasts until the violation is corrected and approved. Under the US federal FAR clause, a contract stop-work order lasts 90 days unless extended, after which the work must be resumed or terminated.

Who pays for delays caused by a stop work order?

It depends on the cause. If the owner stopped the work for its own reasons, the contractor is often entitled to time and cost. If the contractor caused it, for example by working without a permit, the contractor usually bears the cost. The contract decides.