Guaranteed Maximum Price [GMP]

An owners way to ensure a budget is maintained.
Kyle Parry
Kyle Parry
guaranteed maximum price « Back to Glossary Index

In construction, a guaranteed maximum price (GMP) is a contract pricing arrangement where the contractor is paid the actual cost of the work plus a fee, up to an agreed ceiling. The owner will not pay more than the GMP for the agreed scope; cost overruns beyond it are generally the contractor’s responsibility, while savings below it go back to the owner or are shared.

GMP contracts are common with construction management at risk (CMAR) and design-build. In the US, standard forms include AIA A102 (cost plus fee with a GMP) and AIA A133 (construction manager as constructor with a GMP).

How a GMP contract works

  1. The contractor joins the team during design and prices the work as the drawings develop.
  2. At an agreed point the contractor proposes a GMP, with a list of assumptions, clarifications and exclusions.
  3. Once accepted, the contractor buys out the trades and builds on an open-book basis: the owner sees and can audit actual costs.
  4. Each pay application bills actual cost plus fee. Total billing cannot exceed the GMP, as adjusted by approved change orders.
  5. At closeout, any savings are returned or shared according to the contract.

What is included in a GMP

  • Cost of the work: subcontracts, materials, labour and equipment.
  • General conditions: site staff, temporary facilities and services.
  • Contractor’s contingency: for buyout gaps, coordination issues and risks within the contractor’s scope.
  • Allowances: amounts for items not yet fully defined.
  • Fee: the contractor’s overhead and profit, often a percentage of cost.
  • Insurance and bonds, where the contract includes them in the GMP.

GMP vs lump sum vs cost-plus

GMP Lump sum (fixed price) Cost-plus (no cap)
Owner pays Actual cost plus fee, up to the cap The fixed price Actual cost plus fee
Cost overrun risk Mostly contractor, above the cap Contractor Owner
Savings Owner, or shared Contractor Owner
Cost transparency Open book Usually closed Open book
Design needed to price Can be partial Usually complete Minimal

Pros and cons

For owners: a known upper limit, earlier start, and visibility of costs. The trade-off is a higher contractor contingency and fee to cover cap risk, plus more effort reviewing costs.

For contractors: early involvement and a fee on actual cost, but real exposure if the GMP is set on incomplete design without clear exclusions.

Tips for managing a GMP

  • Write assumptions, inclusions and exclusions clearly. Most GMP disputes start there.
  • Track contingency and allowance use in a log the owner can see.
  • Separate true scope changes (change orders) from costs the contractor must absorb.
  • Keep cost records audit-ready from day one.

Related terms

Related templates and guides

Frequently asked questions

Who keeps the savings under a GMP contract?

It depends on the contract. Some GMP agreements return all savings to the owner. Others split savings between owner and contractor by an agreed percentage to reward cost control. Read the savings clause carefully, along with how contingency and allowance savings are treated.

What is the difference between a GMP and a lump sum contract?

With a lump sum, the owner pays a fixed price and the contractor keeps any savings or absorbs any overrun. With a GMP, the owner pays actual costs plus a fee up to a cap, with open-book accounting, and savings below the cap go to the owner or are shared.

Can a guaranteed maximum price change?

Yes, through change orders. Owner-requested scope changes, differing site conditions and other events the contract allows can adjust the GMP. Cost overruns on the work already included in the GMP are normally the contractor’s responsibility.

When is the GMP set?

Often before the design is complete, for example during design development or partway through construction documents, so the contractor can start early. The earlier the GMP is set, the more it relies on contingencies, allowances and clearly written assumptions and exclusions.

Ask AI about this page: ChatGPT, Claude or PerplexityCopy as Markdown

« Back to Glossary Index