Contingency

Contingency is additional time or money allocated to a construction project in order to mitigate risk related to specific items. For example, one may carry ...
Kyle Parry
Kyle Parry
9460F518 3EDE 4F1F AB2E CFC9ACA6556A - Contingency « Back to Glossary Index

Contingency is additional time or money allocated to a construction project in order to mitigate risk related to specific items. For example, one may carry $10,000 in contingency to deal with concealed electrical devices on a project that cannot be identified by just looking at the space.

Contingency is held by the owner, the contractor or both, depending on the contract. It is there to absorb costs that are likely to happen somewhere on the job but cannot be pinned down when the budget is set.

Types of contingency

Type Held by Covers
Design contingency Estimator / owner Scope that will appear as the design is completed
Construction (contractor) contingency Contractor, e.g. under a GMP Buyout gaps, coordination issues and risks in the contractor’s scope
Owner contingency Owner Owner changes, unforeseen conditions, items outside the contractor’s scope
Escalation contingency Owner or contractor Price increases between budget and buyout
Schedule contingency (float or buffer) Contractor or owner Time for delays, weather and late information

Contingency vs allowance

An allowance is a sum for a known item that has not been fully defined yet, such as a door hardware or flooring allowance. The final cost is reconciled against it. A contingency covers the unknown: concealed conditions, errors, coordination problems or market shifts. Keeping them separate makes it clear which money is committed and which is still in reserve.

How to set contingency

Many teams start with a percentage of the estimate, but a better approach is risk-based:

  1. List the risks in a risk register, with likelihood and cost or time impact.
  2. Price the risks, for example using expected monetary value (probability multiplied by impact).
  3. Carry more where the design is incomplete, in renovation and heritage work, on poor or unknown ground, and in volatile markets.
  4. Revisit the amount at each design stage and after buyout.

Managing contingency on site

  • Keep a contingency log showing each draw, its reason and the remaining balance.
  • Use contingency only for its intended purpose. Owner scope changes should go through a change order, not quietly into the contractor’s contingency.
  • Report contingency remaining against risk remaining in every cost report.
  • Release contingency as risks close out, for example after excavation or after buyout.

Related terms

Related templates and guides

Frequently asked questions

What is a good construction contingency percentage?

There is no single right number. It should reflect the risk: how complete the design is, whether it is new build or renovation, site conditions and market volatility. Renovations and early-stage budgets usually carry more. A risk register gives a more defensible number than a flat percentage.

What is the difference between contingency and allowance?

An allowance is money for a known item that is not yet fully defined, such as a carpet allowance per square yard. A contingency covers unknown or unplanned costs. Allowances are reconciled against actual cost; contingency is drawn down only when a risk actually happens.

Who owns the contingency on a construction project?

It depends on the contract. Owners usually hold their own contingency for scope changes and unknowns. Under GMP and some other contracts, the contractor also carries a contingency for risks within its scope. The contract should say who can use each one and what happens to leftovers.

What happens to unused contingency?

Unused owner contingency simply stays in the owner’s budget. Unused contractor contingency in a GMP contract usually returns to the owner or is shared, as the contract sets out. In a lump sum contract, any contingency the contractor priced in is part of its price.

Ask AI about this page: ChatGPT, Claude or PerplexityCopy as Markdown

Merriam-Webster Online Dictionary
contingency (noun)
1.
the quality or state of being - contingent
2.
a event or condition as - contingent
a) an event (as an emergency) that may but is not certain to occur - trying to provide for every contingency
b) something liable to happen as an to or result of something else - adjunct juncture
« Back to Glossary Index